2015.06.30 10Q

 
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, D.C. 20549
 
FORM 10-Q
 
x
QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934
For the quarterly period ended June 30, 2015
OR
o
TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934
For the transition period from                       to                      
Commission File Number 1-12815
 
  CHICAGO BRIDGE & IRON COMPANY N.V.
Incorporated in The Netherlands IRS Identification Number: Not Applicable
 
 Prinses Beatrixlaan 35
2595 AK The Hague
The Netherlands
31-70-3732010
(Address and telephone number of principal executive offices)

Indicate by check mark whether the registrant: (1) has filed all reports required to be filed by Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrant was required to file such reports), and (2) has been subject to such filing requirements for the past 90 days.    
x  Yes    o  No
Indicate by check mark whether the registrant has submitted electronically and posted on its corporate Website, if any, every Interactive Data File required to be submitted and posted pursuant to Rule 405 of Regulation S-T (§232.405 of this chapter) during the preceding 12 months (or for such shorter period that the registrant was required to submit and post such files).    
x  Yes    o  No
Indicate by check mark whether the registrant is a large accelerated filer, an accelerated filer, a non-accelerated filer, or a smaller reporting company. See the definitions of “large accelerated filer,” “accelerated filer” and “smaller reporting company” in Rule 12b-2 of the Exchange Act.
Large accelerated filer
 
x
  
Accelerated filer
 
o
 
 
 
 
 
 
Non-accelerated filer
 
o  (Do not check if a smaller reporting company)
  
Smaller reporting company
 
o
Indicate by check mark whether the registrant is a shell company (as defined in Rule 12b-2 of the Exchange Act).    
o  Yes    x  No
The number of shares outstanding of the registrant’s common stock as of July 17, 2015106,428,590
 




CHICAGO BRIDGE & IRON COMPANY N.V.
Table of Contents
 
 
Page
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 


2

Table of Contents

PART I—FINANCIAL INFORMATION

Item 1. Condensed Consolidated Financial Statements

CHICAGO BRIDGE & IRON COMPANY N.V.
CONDENSED CONSOLIDATED STATEMENTS OF OPERATIONS
(In thousands, except per share data)

 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
2015
 
2014
 
2015
 
2014
 
(Unaudited)
Revenue
$
3,207,113

 
$
3,294,379

 
$
6,332,858

 
$
6,222,511

Cost of revenue
2,823,990

 
2,913,204

 
5,579,564

 
5,539,934

Gross profit
383,123

 
381,175

 
753,294

 
682,577

Selling and administrative expense
85,153

 
98,031

 
194,254

 
217,198

Intangibles amortization
14,942

 
16,822

 
30,594

 
33,056

Equity earnings
(394
)
 
(3,165
)
 
(4,596
)
 
(7,330
)
Other operating (income) expense, net
(685
)
 
(261
)
 
2,137

 
(645
)
Integration related costs

 
9,537

 

 
17,604

Income from operations
284,107

 
260,211

 
530,905

 
422,694

Interest expense
(21,114
)
 
(21,675
)
 
(43,400
)
 
(40,562
)
Interest income
2,184

 
1,477

 
4,232

 
3,537

Income before taxes
265,177

 
240,013

 
491,737

 
385,669

Income tax expense
(79,289
)
 
(72,947
)
 
(149,100
)
 
(115,857
)
Net income
185,888

 
167,066

 
342,637

 
269,812

Less: Net income attributable to noncontrolling interests
(16,373
)
 
(24,662
)
 
(40,894
)
 
(38,457
)
Net income attributable to CB&I
$
169,515

 
$
142,404

 
$
301,743

 
$
231,355

 
 
 
 
 
 
 
 
Net income attributable to CB&I per share:
 
 
 
 
 
 
 
Basic
$
1.56

 
$
1.32

 
$
2.78

 
$
2.14

Diluted
$
1.55

 
$
1.31

 
$
2.76

 
$
2.12

Weighted average shares outstanding:
 
 
 
 
 
 
 
Basic
108,700

 
108,096

 
108,450

 
107,888

Diluted
109,533

 
109,110

 
109,386

 
109,058

Cash dividends on shares:
 
 
 
 
 
 
 
Amount
$
7,610

 
$
7,567

 
$
15,207

 
$
15,126

Per share
$
0.07

 
$
0.07

 
$
0.14

 
$
0.14

The accompanying Notes are an integral part of these Condensed Consolidated Financial Statements.

3

Table of Contents

CHICAGO BRIDGE & IRON COMPANY N.V.
CONDENSED CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME
(In thousands)

 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
2015
 
2014
 
2015
 
2014
 
(Unaudited)
Net income
$
185,888

 
$
167,066

 
$
342,637

 
$
269,812

Other comprehensive income (loss), net of tax:
 
 
 
 
 
 
 
Change in cumulative translation adjustment
24,309

 
7,421

 
(36,125
)
 
12,952

Change in unrealized fair value of cash flow hedges
644

 
(551
)
 
(80
)
 
(1,541
)
Change in unrecognized prior service pension credits/costs
16

 
(92
)
 
(520
)
 
(135
)
Change in unrecognized actuarial pension gains/losses
(4,619
)
 
418

 
9,999

 
2,213

Comprehensive income
206,238

 
174,262

 
315,911

 
283,301

Net income attributable to noncontrolling interests
(16,373
)
 
(24,662
)
 
(40,894
)
 
(38,457
)
Change in cumulative translation adjustment attributable to noncontrolling interests
(217
)
 
(4,323
)
 
1,121

 
(5,974
)
Comprehensive income attributable to CB&I
$
189,648

 
$
145,277

 
$
276,138

 
$
238,870

The accompanying Notes are an integral part of these Condensed Consolidated Financial Statements.

4

Table of Contents

CHICAGO BRIDGE & IRON COMPANY N.V.
CONDENSED CONSOLIDATED BALANCE SHEETS
(In thousands)

 
June 30,
2015
 
December 31,
2014
 
(Unaudited)
 
 
Assets
 
 
 
Cash and cash equivalents ($192,219 and $191,464 related to variable interest entities ("VIEs"))
$
355,088

 
$
351,323

Accounts receivable, net ($298,294 and $235,018 related to VIEs)
1,326,858

 
1,306,567

Inventory
292,244

 
286,155

Costs and estimated earnings in excess of billings ($38,110 and $29,677 related to VIEs)
1,605,190

 
774,644

Deferred income taxes
519,573

 
572,987

Other current assets ($247,027 and $104,447 related to VIEs)
378,532

 
238,783

Total current assets
4,477,485

 
3,530,459

Equity investments
132,480

 
107,984

Property and equipment, net ($20,439 and $21,868 related to VIEs)
741,469

 
771,651

Deferred income taxes
79,762

 
89,196

Goodwill
4,177,038

 
4,195,231

Other intangibles, net
517,804

 
556,454

Other non-current assets
160,824

 
130,056

Total assets
$
10,286,862

 
$
9,381,031

Liabilities
 
 
 
Revolving facility and other short-term borrowings
$
596,740

 
$
164,741

Current maturities of long-term debt
131,096

 
105,997

Accounts payable ($217,676 and $279,597 related to VIEs)
1,179,056

 
1,256,854

Other current liabilities
874,746

 
804,294

Billings in excess of costs and estimated earnings ($647,741 and $282,351 related to VIEs)
2,189,584

 
1,985,488

Deferred income taxes
4,333

 
4,856

Total current liabilities
4,975,555

 
4,322,230

Long-term debt
1,486,085

 
1,564,158

Other non-current liabilities
430,359

 
450,626

Deferred income taxes
211,473

 
167,714

Total liabilities
7,103,472

 
6,504,728

Shareholders’ Equity
 
 
 
Common stock, Euro .01 par value; shares authorized: 250,000; shares issued: 108,757 and 108,407; shares outstanding: 108,738 and 107,806
1,286

 
1,283

Additional paid-in capital
783,761

 
776,864

Retained earnings
2,533,306

 
2,246,770

Treasury stock, at cost: 19 and 601 shares
(947
)
 
(24,428
)
Accumulated other comprehensive loss
(288,002
)
 
(262,397
)
Total CB&I shareholders’ equity
3,029,404

 
2,738,092

Noncontrolling interests
153,986

 
138,211

Total shareholders’ equity
3,183,390

 
2,876,303

Total liabilities and shareholders’ equity
$
10,286,862

 
$
9,381,031

The accompanying Notes are an integral part of these Condensed Consolidated Financial Statements.

5

Table of Contents

CHICAGO BRIDGE & IRON COMPANY N.V.
CONDENSED CONSOLIDATED STATEMENTS OF CASH FLOWS
(In thousands)
 
Six Months Ended June 30,
 
2015
 
2014
 
(Unaudited)
Cash Flows from Operating Activities
 
 
 
Net income
$
342,637

 
$
269,812

Adjustments to reconcile net income to net cash used in operating activities:
 
 
 
Depreciation and amortization
86,699

 
89,870

Deferred taxes
101,035

 
38,685

Stock-based compensation expense
37,767

 
49,317

Equity earnings
(4,596
)
 
(7,330
)
Other operating expense (income), net
2,137

 
(645
)
Unrealized loss on foreign currency hedges
1,559

 
1,612

Excess tax benefits from stock-based compensation
(280
)
 
(15,680
)
Changes in operating assets and liabilities:
 
 
 
Increase in receivables, net
(20,291
)
 
(121,013
)
Change in contracts in progress, net
(626,450
)
 
(797,126
)
(Increase) decrease in inventory
(6,089
)
 
10,897

(Decrease) increase in accounts payable
(77,798
)
 
95,955

(Increase) decrease in other current and non-current assets
(28,096
)
 
1,052

(Decrease) increase in other current and non-current liabilities
(42,675
)
 
989

Decrease in equity investments
23,626

 
15,823

Change in other, net
16,111

 
(6,581
)
Net cash used in operating activities
(194,704
)
 
(374,363
)
Cash Flows from Investing Activities
 
 
 
Capital expenditures
(63,717
)
 
(58,179
)
Advances to partners of proportionately consolidated ventures, net
(122,436
)
 

Proceeds from sale of property and equipment
3,292

 
9,031

Change in other, net
(6,783
)
 

Net cash used in investing activities
(189,644
)
 
(49,148
)
Cash Flows from Financing Activities
 
 
 
Revolving facility and other short-term borrowings, net
431,999

 
494,266

Advances from proportionately consolidated ventures, net
84,936

 

Repayments on long-term debt
(52,974
)
 
(50,000
)
Excess tax benefits from stock-based compensation
280

 
15,680

Purchase of treasury stock
(13,887
)
 
(66,591
)
Issuance of stock
11,074

 
17,610

Dividends paid
(15,207
)
 
(15,126
)
Distributions to noncontrolling interests
(23,998
)
 
(38,556
)
Net cash provided by financing activities
422,223

 
357,283

Effect of exchange rate changes on cash and cash equivalents
(34,110
)
 
20,039

Increase (decrease) in cash and cash equivalents
3,765

 
(46,189
)
Cash and cash equivalents, beginning of the year
351,323

 
420,502

Cash and cash equivalents, end of the period
$
355,088

 
$
374,313


The accompanying Notes are an integral part of these Condensed Consolidated Financial Statements.


6

Table of Contents

CHICAGO BRIDGE & IRON COMPANY N.V.
CONDENSED CONSOLIDATED STATEMENTS OF CHANGES IN SHAREHOLDERS’ EQUITY
(In thousands, except per share data)

 
Common Stock
 
Additional
Paid-In
 
Retained
 
Treasury Stock
 

Accumulated
Other
Comprehensive
 
Non -
controlling
 
Total
Shareholders’
 
Shares
 
Amount
 
Capital
 
Earnings
 
Shares
 
Amount
 
(Loss) Income
 
Interests
 
Equity
 
 (Unaudited)
Balance at December 31, 2014
107,806

 
$
1,283

 
$
776,864

 
$
2,246,770

 
601

 
$
(24,428
)
 
$
(262,397
)
 
$
138,211

 
$
2,876,303

Net income

 

 

 
301,743

 

 

 

 
40,894

 
342,637

Change in cumulative translation adjustment, net

 

 

 

 

 

 
(35,004
)
 
(1,121
)
 
(36,125
)
Change in unrealized fair value of cash flow hedges, net

 

 

 

 

 

 
(80
)
 

 
(80
)
Change in unrecognized prior service pension credits/costs, net

 

 

 

 

 

 
(520
)
 

 
(520
)
Change in unrecognized actuarial pension gains/losses, net

 

 

 

 

 

 
9,999

 

 
9,999

Distributions to noncontrolling interests

 

 

 

 

 

 

 
(23,998
)
 
(23,998
)
Dividends paid ($0.14 per share)

 

 

 
(15,207
)
 

 

 

 

 
(15,207
)
Stock-based compensation expense

 

 
37,767

 

 

 

 

 

 
37,767

Issuance to treasury stock

 
3

 
15,348

 

 
350

 
(15,351
)
 

 

 

Purchase of treasury stock
(339
)
 

 

 

 
339

 
(13,887
)
 

 

 
(13,887
)
Issuance of stock
1,271

 

 
(46,218
)
 

 
(1,271
)
 
52,719

 

 

 
6,501

Balance at June 30, 2015
108,738

 
$
1,286

 
$
783,761

 
$
2,533,306

 
19

 
$
(947
)
 
$
(288,002
)
 
$
153,986

 
$
3,183,390

 
Common Stock
 
Additional
Paid-In
 
Retained
 
Treasury Stock
 
Accumulated
Other
Comprehensive
 
Non -
controlling
 
Total
Shareholders’
 
Shares
 
Amount
 
Capital
 
Earnings
 
Shares
 
Amount
 
(Loss) Income
 
Interests
 
Equity
 
 (Unaudited)
Balance at December 31, 2013
107,478

 
$
1,275

 
$
753,742

 
$
1,733,409

 
379

 
$
(23,914
)
 
$
(119,933
)
 
$
162,859

 
$
2,507,438

Net income

 

 

 
231,355

 

 

 

 
38,457

 
269,812

Change in cumulative translation adjustment, net

 

 

 

 

 

 
6,978

 
5,974

 
12,952

Change in unrealized fair value of cash flow hedges, net

 

 

 

 

 

 
(1,541
)
 

 
(1,541
)
Change in unrecognized prior service pension credits/costs, net

 

 

 

 

 

 
(135
)
 

 
(135
)
Change in unrecognized actuarial pension gains/losses, net

 

 

 

 

 

 
2,213

 

 
2,213

Distributions to noncontrolling interests

 

 

 

 

 

 

 
(38,556
)
 
(38,556
)
Dividends paid ($0.14 per share)

 

 

 
(15,126
)
 

 

 

 

 
(15,126
)
Stock-based compensation expense

 

 
49,317

 

 

 

 

 

 
49,317

Issuance to treasury stock

 
5

 
28,626

 

 
350

 
(28,631
)
 

 

 

Purchase of treasury stock
(863
)
 

 

 

 
863

 
(66,591
)
 

 

 
(66,591
)
Issuance of stock
1,497

 

 
(77,724
)
 

 
(1,497
)
 
111,607

 

 

 
33,883

Balance at June 30, 2014
108,112

 
$
1,280

 
$
753,961

 
$
1,949,638

 
95

 
$
(7,529
)
 
$
(112,418
)
 
$
168,734

 
$
2,753,666


The accompanying Notes are an integral part of these Condensed Consolidated Financial Statements.


7

Table of Contents

CHICAGO BRIDGE & IRON COMPANY N.V.
NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS
June 30, 2015
($ and share values in thousands, except per share data)
(Unaudited)
1. ORGANIZATION AND NATURE OF OPERATIONS
Organization and Nature of Operations—Founded in 1889, Chicago Bridge & Iron Company N.V. (“CB&I” or the “Company”) provides a wide range of services, including conceptual design, technology, engineering, procurement, fabrication, modularization, construction, commissioning, maintenance, program management and environmental services to customers in the energy infrastructure market throughout the world, and is a provider of diversified government services. Our business is aligned into four operating groups, which represent our reportable segments. During the first quarter 2015, we realigned our four operating groups to reflect the present management oversight of our operations: (1) Engineering & Construction (formerly Engineering, Construction & Maintenance); (2) Fabrication Services; (3) Technology; and (4) Capital Services (formerly Environmental Solutions). See Note 15 for a discussion of our realigned operating groups and related financial information.
2. SIGNIFICANT ACCOUNTING POLICIES
Basis of Accounting and Consolidation—The accompanying unaudited interim Condensed Consolidated Financial Statements (“Financial Statements”) are prepared in accordance with the rules and regulations of the United States (“U.S.”) Securities and Exchange Commission (the “SEC”) and accounting principles generally accepted in the United States of America (“U.S. GAAP”). These Financial Statements include all wholly-owned subsidiaries and those entities which we are required to consolidate. See the “Partnering Arrangements” section of this footnote for further discussion of our consolidation policy for those entities that are not wholly-owned. Significant intercompany balances and transactions are eliminated in consolidation.
Basis of Presentation—We believe these Financial Statements include all adjustments, which are of a normal recurring nature, necessary for a fair presentation of our results of operations for the three and six months ended June 30, 2015 and 2014, our financial position as of June 30, 2015 and our cash flows for the six months ended June 30, 2015 and 2014. The December 31, 2014 Condensed Consolidated Balance Sheet was derived from our December 31, 2014 audited Consolidated Balance Sheet.
We believe the disclosures accompanying these Financial Statements are adequate to make the information presented not misleading. Certain information and footnote disclosures normally included in annual financial statements prepared in accordance with U.S. GAAP have been condensed or omitted pursuant to the rules and regulations of the SEC for interim reporting periods. The results of operations and cash flows for the interim periods are not necessarily indicative of the results to be expected for the full year. The accompanying Financial Statements should be read in conjunction with our Consolidated Financial Statements and notes thereto included in our 2014 Annual Report on Form 10-K (“2014 Annual Report”).
Use of Estimates—The preparation of our Financial Statements in conformity with U.S. GAAP requires us to make estimates and judgments that affect the reported amounts of assets, liabilities, revenue and expenses and related disclosures of contingent assets and liabilities. We believe the most significant estimates and judgments are associated with revenue recognition for our contracts, including estimating costs and the recognition of incentive fees and unapproved change orders and claims; fair value and recoverability assessments that must be periodically performed with respect to long-lived tangible assets, goodwill and other intangible assets; valuation of deferred tax assets and financial instruments; the determination of liabilities related to self-insurance programs and income taxes; and consolidation determinations with respect to our partnering arrangements. If the underlying estimates and assumptions upon which our Financial Statements are based change in the future, actual amounts may differ from those included in the accompanying Financial Statements.
Revenue Recognition—Our revenue is primarily derived from long-term contracts and is generally recognized using the percentage of completion (“POC”) method, primarily based on the percentage that actual costs-to-date bear to total estimated costs to complete each contract. We follow the guidance of Financial Accounting Standards Board (“FASB”) Accounting Standards Codification (“ASC”) Revenue Recognition Topic 605-35 for accounting policies relating to our use of the POC method, estimating costs, and revenue recognition, including the recognition of incentive fees, unapproved change orders and claims, and combining and segmenting contracts. We primarily utilize the cost-to-cost approach to estimate POC as we believe this method is less subjective than relying on assessments of physical progress. Under the cost-to-cost approach, the use of estimated costs to complete each contract is a significant variable in the process of determining recognized revenue and is a significant factor in the accounting for contracts. Significant estimates that impact the cost to complete each contract are costs of engineering, materials, components, equipment, labor and subcontracts; labor productivity; schedule durations, including subcontractor or supplier progress; liquidated damages; contract disputes, including claims; achievement of contractual performance requirements; and contingency, among others. The cumulative impact of revisions in total cost estimates during

8

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

the progress of work is reflected in the period in which these changes become known, including, to the extent required, the reversal of profit recognized in prior periods and the recognition of losses expected to be incurred on contracts in progress. Due to the various estimates inherent in our contract accounting, actual results could differ from those estimates. Backlog for each of our operating groups generally consists of several hundred contracts and our results may be impacted by changes in estimated project margins. For the three and six months ended June 30, 2015, individual projects with significant changes in estimated margins resulted in a net increase to our income from operations of approximately $16,000. For the three and six months ended June 30, 2014, individual projects with significant changes in estimated margins resulted in a net increase to income from operations of approximately $29,000.
Our long-term contracts are awarded on a competitively bid and negotiated basis and the timing of revenue recognition may be impacted by the terms of such contracts. We use a range of contracting options, including cost-reimbursable, fixed-price and hybrid, which has both cost-reimbursable and fixed-price characteristics. Fixed-price contracts, and hybrid contracts with a more significant fixed-price component, tend to provide us with greater control over project schedule and the timing of when work is performed and costs are incurred, and accordingly, when revenue is recognized. Cost-reimbursable contracts, and hybrid contracts with a more significant cost-reimbursable component, generally provide our customers with greater influence over the timing of when we perform our work, and accordingly, such contracts often result in less predictability with respect to the timing of revenue recognition. Contract revenue for our long-term contracts recognized under the POC method reflects the original contract price adjusted for approved change orders and estimated recoveries for incentive fees, unapproved change orders and claims. We recognize revenue associated with incentive fees when the value can be reliably estimated and recovery is probable. We recognize revenue associated with unapproved change orders and claims to the extent the related costs have been incurred, the value can be reliably estimated and recovery is probable. Our recorded incentive fees, unapproved change orders and claims reflect our best estimate of recovery amounts; however, the ultimate resolution and amounts received could differ from these estimates. See Note 14 for additional discussion of our recorded unapproved change orders, claims, incentives and other contract recoveries.
With respect to our engineering, procurement, and construction (“EPC”) services, our contracts are not segmented between types of services, such as engineering and construction, if each of the EPC components is negotiated concurrently or if the pricing of any such services is subject to the ultimate negotiation and agreement of the entire EPC contract. However, an EPC contract including technology or fabrication services may be segmented if we satisfy the segmenting criteria in ASC 605-35. Revenue recorded in these situations is based on our prices and terms for similar services to third party customers. Segmenting a contract may result in different interim rates of profitability for each scope of service than if we had recognized revenue without segmenting. In some instances, we may combine contracts that are entered into in multiple phases, but are interdependent and include pricing considerations by us and the customer that are impacted by all phases of the project. Otherwise, if each phase is independent of the other and pricing considerations do not give effect to another phase, the contracts will not be combined.
Cost of revenue for our long-term contracts includes direct contract costs, such as materials and labor, and indirect costs that are attributable to contract activity. The timing of when we bill our customers is generally dependent upon advance billing terms, milestone billings based on the completion of certain phases of the work, or when services are provided. Projects with cumulative costs and estimated earnings recognized to date in excess of cumulative billings is reported on the Condensed Consolidated Balance Sheet (“Balance Sheet”) as costs and estimated earnings in excess of billings. Projects with cumulative billings in excess of costs and estimated earnings recognized to date is reported on the Balance Sheet as billings in excess of costs and estimated earnings. The net balances on our Balance Sheet are collectively referred to as Contracts in Progress, net, and the components of these balances at June 30, 2015 and December 31, 2014 were as follows:
 
 
June 30, 2015
 
December 31, 2014
 
 
Asset
 
Liability
 
Asset
 
Liability
Costs and estimated earnings on contracts in progress
 
$
22,728,277

 
$
23,308,188

 
$
20,119,444

 
$
26,052,767

Billings on contracts in progress
 
(21,123,087
)
 
(24,995,597
)
 
(19,344,800
)
 
(27,479,495
)
Margin fair value liability for acquired contracts (1)
 

 
(502,175
)
 

 
(558,760
)
Contracts in Progress, net
 
$
1,605,190

 
$
(2,189,584
)
 
$
774,644

 
$
(1,985,488
)
(1)
The balance represents a margin fair value liability associated with long-term contracts acquired in connection with our acquisition of The Shaw Group Inc. on February 13, 2013 (the "Acquisition Closing Date"). The margin fair value liability was approximately $745,500 at the Acquisition Closing Date and is recognized as revenue on a POC basis as the applicable projects progress. We anticipate the remaining liability will be recognized as revenue over the next five years. Revenue and the related income from operations recognized during the three and six months ended June 30, 2015

9

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

was approximately $24,600 and $56,600, respectively, compared with approximately $33,800 and $61,300, respectively, for the comparable 2014 periods.
Any uncollected billed amounts, including contract retentions, are reported as accounts receivable. At June 30, 2015 and December 31, 2014, accounts receivable included contract retentions of approximately $58,200 and $53,000, respectively. Contract retentions due beyond one year were not material at June 30, 2015 or December 31, 2014.
Revenue for our service contracts that do not satisfy the criteria for revenue recognition under the POC method is recorded at the time services are performed. Revenue associated with incentive fees for these contracts is recognized when earned. Unbilled receivables for our service contracts are recorded within accounts receivable and were approximately $83,100 and $66,900 at June 30, 2015 and December 31, 2014, respectively.
Revenue for our pipe and steel fabrication and catalyst manufacturing contracts that are independent of an EPC contract, or for which we satisfy the segmentation criteria discussed above, is recognized upon shipment of the fabricated or manufactured units. During the fabrication or manufacturing process, all related direct and allocable indirect costs are capitalized as work in process inventory and such costs are recorded as cost of revenue at the time of shipment.
Our billed and unbilled revenue may be exposed to potential credit risk if our customers should encounter financial difficulties, and we maintain reserves for specifically-identified potential uncollectible receivables. At June 30, 2015 and December 31, 2014, our allowances for doubtful accounts were not material.
Other Operating Expense (Income), Net—Other operating expense (income), net, generally represents losses (gains) associated with the sale or disposition of property and equipment. For the six months ended June 30, 2015, other operating expense (income) also included a gain of approximately $7,500 related to the contribution of a technology to our unconsolidated Chevron-Lummus Global ("CLG") joint venture and a foreign exchange loss of approximately $11,000 associated with the re-measurement of certain non-U.S. Dollar denominated net assets, both of which occurred during the three months ended March 31, 2015.
Integration Related Costs—For the three and six months ended June 30, 2014, integration related costs of $9,537 and $17,604, respectively, primarily related to facility consolidations, including the associated accrued future lease costs for vacated facilities and unutilized capacity, personnel relocation and severance related costs, and systems integration costs.
Recoverability of Goodwill—Goodwill is not amortized to earnings, but instead is reviewed for impairment at least annually at a reporting unit level, absent any indicators of impairment. We perform our annual impairment assessment during the fourth quarter of each year based upon balances as of October 1. At December 31, 2014, we had the following seven reporting units within our four operating groups:
Engineering, Construction & Maintenance—Our Engineering, Construction & Maintenance operating group included three reporting units: Oil & Gas, Power and Plant Services.
Fabrication Services—Our Fabrication Services operating group included two reporting units: Steel Plate Structures and Fabrication & Manufacturing.
Technology—Our Technology operating group represented a reporting unit.
Environmental Solutions—Our Environmental Solutions operating group represented a reporting unit.
As part of our annual impairment assessment, in the fourth quarter 2014, we performed a quantitative assessment of goodwill for each of the aforementioned reporting units. Based upon this quantitative assessment, the fair value of each of our reporting units exceeded their respective net book values, and accordingly, no impairment charge was necessary during 2014.
During the three months ended March 31, 2015, we realigned our four operating groups, which represent our reportable segments, as discussed further in Note 15. In connection therewith, we realigned our reporting units, and accordingly, we currently have the following eight reporting units within our four realigned operating groups:
Engineering & Construction (formerly Engineering, Construction & Maintenance)—Our Engineering & Construction operating group includes two reporting units: Oil & Gas and Power. Our Plant Services reporting unit was reclassified to our realigned Capital Services operating group, as noted below.
Fabrication Services—Our Fabrication Services operating group includes three reporting units: Steel Plate Structures, Fabrication & Manufacturing, and Engineered Products. Our Engineered Products reporting unit represents a portion of our previous Technology reporting unit.

10

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

Technology—Our Technology operating group continues to represent a reporting unit, consisting of the remaining portion of our previous Technology reporting unit, after reclassification of the Engineered Products reporting unit to Fabrication Services, as noted above.
Capital Services (formerly Environmental Solutions)—Our Capital Services operating group includes two reporting units: Facilities & Plant Services and Federal Services. Our Facilities & Plant Services reporting unit represents our previous Plant Services reporting unit and a portion of our previous Environmental Solutions reporting unit. Our Federal Services reporting unit represents the remaining portion of our previous Environmental Solutions reporting unit.
In conjunction with the aforementioned realignment of our operating groups, we allocated goodwill among our new and realigned reporting units based on the relative fair value of the reporting units being realigned. As a result, during the three months ended March 31, 2015, we performed a quantitative assessment of goodwill for each of the reporting units impacted by our operating group realignment, which included Engineered Products, Technology, Facilities & Plant Services, and Federal Services. Based on this quantitative assessment, the fair value of each of the reporting units impacted by our operating group realignment exceeded their respective net book values, and accordingly, no impairment charge was necessary as a result of the realignment. Additionally, during the six months ended June 30, 2015, no indicators of goodwill impairment were identified for any of our reporting units. If, based on future assessments our goodwill is deemed to be impaired, the impairment would result in a charge to earnings in the period of impairment.
To determine the fair value of our reporting units and test for impairment, we utilized an income approach (discounted cash flow method) as we believe this is the most direct approach to incorporate the specific economic attributes and risk profiles of our reporting units into our valuation model. This is consistent with the methodology used to determine the fair value of our reporting units in previous years. We generally do not utilize a market approach given the lack of relevant information generated by market transactions involving comparable businesses. See Note 5 for additional disclosures associated with our goodwill.
Recoverability of Other Long-Lived Assets—We amortize our finite-lived intangible assets on a straight-line basis with lives ranging from 3 to 20 years, absent any indicators of impairment. We review tangible assets and finite-lived intangible assets for impairment when events or changes in circumstances indicate that the carrying amount may not be recoverable. If a recoverability assessment is required, the estimated future cash flow associated with the asset or asset group will be compared to the asset’s carrying amount to determine if an impairment exists. We noted no indicators of impairment during the six months ended June 30, 2015. See Note 5 for additional disclosures associated with our intangible assets.
Earnings Per Share (“EPS”)—Basic EPS is calculated by dividing net income attributable to CB&I by the weighted average number of common shares outstanding for the period. Diluted EPS reflects the assumed conversion of dilutive securities, consisting of restricted shares, performance shares (where performance criteria have been met), stock options and directors’ deferred-fee shares. See Note 3 for calculations associated with basic and diluted EPS.
Cash Equivalents—Cash equivalents are considered to be highly liquid securities with original maturities of three months or less.
Inventory—Inventory is recorded at the lower of cost or market and cost is determined using the first-in-first-out or weighted-average cost method. The cost of inventory includes acquisition costs, production or conversion costs, and other costs incurred to bring the inventory to a current location and condition. An allowance for excess or inactive inventory is recorded based upon an analysis that considers current inventory levels, historical usage patterns, estimates of future sales expectations and salvage value. See Note 4 for additional disclosures associated with our inventory.
Foreign Currency—The nature of our business activities involves the management of various financial and market risks, including those related to changes in foreign currency exchange rates. The effects of translating financial statements of foreign operations into our reporting currency are recognized as a cumulative translation adjustment in accumulated other comprehensive income (loss) (“AOCI”) which is net of tax, where applicable. With the exception of a foreign exchange loss of approximately $11,000 included within other operating expense (income), net related to the re-measurement of certain non-U.S. Dollar denominated net assets during the three months ended March 31, 2015, foreign currency transactional and re-measurement exchange gains (losses) are included within cost of revenue and were not material for the three and six months ended June 30, 2015 and 2014.
Financial Instruments—We utilize derivative instruments in certain circumstances to mitigate the effects of changes in foreign currency exchange rates and interest rates, as described below:
Foreign Currency Exchange Rate Derivatives—We do not engage in currency speculation; however, we utilize foreign currency exchange rate derivatives on an ongoing basis to hedge against certain foreign currency-related operating

11

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

exposures. We generally seek hedge accounting treatment for contracts used to hedge operating exposures and designate them as cash flow hedges. Therefore, gains and losses, exclusive of credit risk and forward points (which represent the time-value component of the fair value of our derivative positions), are included in AOCI until the associated underlying operating exposure impacts our earnings. Changes in the fair value of (1) credit risk and forward points, (2) instruments deemed ineffective during the period, and (3) instruments that we do not designate as cash flow hedges are recognized within cost of revenue.
Interest Rate Derivatives—At June 30, 2015, we continued to utilize a swap arrangement to hedge against interest rate variability associated with $391,375 of our outstanding $775,000 unsecured term loan (the “Term Loan”). The swap arrangement has been designated as a cash flow hedge as its critical terms matched those of the Term Loan at inception and through June 30, 2015. Accordingly, changes in the fair value of the swap arrangement are included in AOCI until the associated underlying exposure impacts our earnings.
For those contracts designated as cash flow hedges, we document all relationships between the derivative instruments and associated hedged items, as well as our risk-management objectives and strategy for undertaking hedge transactions. This process includes linking all derivatives to specific firm commitments or highly-probable forecasted transactions. We continually assess, at inception and on an ongoing basis, the effectiveness of derivative instruments in offsetting changes in the cash flow of the designated hedged items. Hedge accounting designation is discontinued when (1) it is determined that the derivative is no longer highly effective in offsetting changes in the cash flow of the hedged item, including firm commitments or forecasted transactions, (2) the derivative is sold, terminated, exercised, or expires, (3) it is no longer probable that the forecasted transaction will occur, or (4) we determine that designating the derivative as a hedging instrument is no longer appropriate. See Note 9 for additional discussion of our financial instruments.
Income Taxes—Deferred tax assets and liabilities are recognized for the future tax consequences attributable to differences between the financial statement carrying amounts of existing assets and liabilities and their respective tax basis using currently enacted income tax rates for the years in which the differences are expected to reverse. A valuation allowance is provided to offset any net deferred tax assets (“DTA(s)”) if, based upon the available evidence, it is more likely than not that some or all of the DTAs will not be realized. The realization of our net DTAs depends upon our ability to generate sufficient future taxable income of the appropriate character and in the appropriate jurisdictions.
Income tax and associated interest reserves, where applicable, are recorded in those instances where we consider it more likely than not that additional tax will be due in excess of amounts reflected in income tax returns filed worldwide, irrespective of whether or not we have received tax assessments. We continually review our exposure to additional income tax obligations and, as further information is known or events occur, changes in our tax and interest reserves may be recorded within income tax expense and interest expense, respectively.
Partnering ArrangementsIn the ordinary course of business, we execute specific projects and conduct certain operations through joint venture, consortium and other collaborative arrangements (collectively referred to as “venture(s)”). We have various ownership interests in these ventures, with such ownership typically being proportionate to our decision-making and distribution rights. The ventures generally contract directly with the third party customer; however, services may be performed directly by the ventures, or may be performed by us, our partners, or a combination thereof.
Venture net assets consist primarily of working capital and property and equipment, and assets may be restricted from being used to fund obligations outside of the venture. These ventures typically have limited third party debt or have debt that is non-recourse in nature; however, they may provide for capital calls to fund operations or require participants in the venture to provide additional financial support, including advance payment or retention letters of credit.
Each venture is assessed at inception and on an ongoing basis as to whether it qualifies as a VIE under the consolidations guidance in ASC 810. A venture generally qualifies as a VIE when it (1) meets the definition of a legal entity, (2) absorbs the operational risk of the projects being executed, creating a variable interest, and (3) lacks sufficient capital investment from the partners, potentially resulting in the venture requiring additional subordinated financial support, if necessary, to finance its future activities.
If at any time a venture qualifies as a VIE, we perform a qualitative assessment to determine whether we are the primary beneficiary of the VIE and, therefore, need to consolidate the VIE. We are the primary beneficiary if we have (1) the power to direct the economically significant activities of the VIE and (2) the right to receive benefits from, and obligation to absorb losses of, the VIE. If the venture is a VIE and we are the primary beneficiary, or we otherwise have the ability to control the venture, we consolidate the venture. If we are not determined to be the primary beneficiary of the VIE, or only have the ability to significantly influence, rather than control the venture, we do not consolidate the venture. We account for unconsolidated ventures using proportionate consolidation for both our Balance Sheet and Statement of Operations when we meet the

12

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

applicable accounting criteria to do so and utilize the equity method otherwise. See Note 6 for additional discussion of our material partnering arrangements.
New Accounting Standards—In May 2014, the FASB issued Accounting Standards Update ("ASU") 2014-09, which provides a single comprehensive accounting standard for revenue recognition for contracts with customers and supersedes current industry-specific guidance, including ASC 605-35. Upon adoption of ASU 2014-09, entities are required to recognize revenue using the following comprehensive model: (1) identify the contract with a customer, (2) identify the performance obligations in the contract, (3) determine the transaction price, (4) allocate the transaction price to the performance obligations in the contract, and (5) recognize revenue as the entity satisfies each performance obligation. ASU 2014-09 is effective for us beginning in the first quarter 2018. Our adoption of ASU 2014-09 will result in retrospective application, either in the form of recasting all prior periods presented or a cumulative adjustment to equity in the period of adoption. We are assessing the impact that the new standard will have on our Financial Statements.
In February 2015, the FASB issued ASU 2015-02, which amends existing consolidation requirements in ASC 810 and will require entities to evaluate their consolidation analysis for subsidiaries that are not wholly-owned. ASU 2015-02, which is effective for us beginning in the first quarter 2016, includes amended guidance associated with: (1) determining the consolidation model and assessing control for limited partnerships and similar entities; (2) determining when fees paid to decision makers or service providers are variable interests; and (3) evaluating interests held by de facto agents or related parties of the reporting entity. We are assessing the impact that the new standard will have on our Financial Statements.
In April 2015, the FASB issued ASU 2015-03, which changes the presentation of debt issuance costs. Upon adoption, debt issuance costs would be presented as a direct deduction from the related debt liability rather than as an asset, as currently presented. ASU 2015-03 is effective for us beginning in the first quarter 2016. We do not believe the new standard will have a material impact on our Financial Statements.
3. EARNINGS PER SHARE
A reconciliation of weighted average basic shares outstanding to weighted average diluted shares outstanding and the computation of basic and diluted EPS are as follows:
 
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
 
2015
 
2014
 
2015
 
2014
Net income attributable to CB&I
 
$
169,515

 
$
142,404

 
$
301,743

 
$
231,355

Weighted average shares outstanding—basic
 
108,700

 
108,096

 
108,450

 
107,888

Effect of restricted shares/performance shares/stock options (1)
 
822

 
980

 
926

 
1,118

Effect of directors’ deferred-fee shares
 
11

 
34

 
10

 
52

Weighted average shares outstanding—diluted
 
109,533

 
109,110

 
109,386

 
109,058

Net income attributable to CB&I per share:
 
 
 
 
 
 
 
 
Basic
 
$
1.56

 
$
1.32

 
$
2.78

 
$
2.14

Diluted
 
$
1.55

 
$
1.31

 
$
2.76

 
$
2.12

(1)
Antidilutive shares excluded from diluted EPS were not material for the three and six months ended June 30, 2015 or 2014.
4. INVENTORY
The components of inventory at June 30, 2015 and December 31, 2014 were as follows:
 
June 30,
2015
 
December 31,
2014
Raw materials
$
157,241

 
$
162,451

Work in process
38,508

 
38,232

Finished goods
96,495

 
85,472

Total
$
292,244

 
$
286,155


13

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

5. GOODWILL AND OTHER INTANGIBLES
Goodwill—At June 30, 2015 and December 31, 2014, our goodwill balances were $4,177,038 and $4,195,231, respectively, attributable to the excess of the purchase price over the fair value of net assets acquired in connection with our acquisitions. The change in goodwill for the six months ended June 30, 2015 was as follows:
 
 
Total
Balance at December 31, 2014
 
$
4,195,231

Foreign currency translation
 
(15,806
)
Amortization of tax goodwill in excess of book goodwill
 
(2,387
)
Balance at June 30, 2015
 
$
4,177,038

As discussed further in Note 2, in conjunction with the realignment of our operating groups during the three months ended March 31, 2015, we performed a quantitative assessment of goodwill for our realigned reporting units. Based on this quantitative assessment, no impairment charge was necessary as a result of the realignment. Additionally, during the six months ended June 30, 2015, no indicators of goodwill impairment were identified for any of our reporting units. There can be no assurance that future goodwill impairment tests will not result in charges to earnings.
Other Intangible Assets—The following table provides a summary of our finite-lived intangible assets at June 30, 2015 and December 31, 2014, including weighted-average useful lives for each major intangible asset class and in total:
 
 
 
 
June 30, 2015
 
December 31, 2014
 
 
Weighted Average Life
 
Gross
Carrying
Amount
 
Accumulated
Amortization
 
Gross
Carrying
Amount
 
Accumulated
Amortization
Finite-lived intangible assets
 
 
 
 
 
 
 
 
 
 
Backlog and customer relationships (1)
 
17 years
 
$
369,572

 
$
(77,203
)
 
$
380,586

 
$
(71,257
)
Process technologies
 
15 years
 
272,440

 
(107,448
)
 
287,459

 
(105,646
)
Tradenames
 
10 years
 
85,364

 
(24,921
)
 
85,613

 
(20,301
)
Total (2)
 
16 years
 
$
727,376

 
$
(209,572
)
 
$
753,658

 
$
(197,204
)
(1) 
Backlog and customer relationships intangibles totaling approximately $11,000 became fully amortized during the three months ended March 31, 2015 and were therefore removed from the gross carrying and accumulated amortization balances above.
(2) 
The decrease in other intangible assets during the six months ended June 30, 2015 primarily related to amortization expense of approximately $30,600 and the impact of foreign currency translation.
6. PARTNERING ARRANGEMENTS
As discussed in Note 2, we account for our unconsolidated ventures using either proportionate consolidation or the equity method. Further, we consolidate any venture that is determined to be a VIE for which we are the primary beneficiary, or which we otherwise effectively control.
Proportionately Consolidated Ventures—The following is a summary description of our significant unconsolidated joint ventures which have been accounted for using proportionate consolidation:
CB&I/Zachry—We have a venture with Zachry (CB&I—50% / Zachry—50%) to perform EPC work for two liquefied natural gas (“LNG”) liquefaction trains in Freeport, Texas. Our proportionate share of the venture project value is approximately $2,600,000. In addition, we have subcontract and risk sharing arrangements with Chiyoda to support our responsibilities to the venture. The costs of these arrangements are recorded in cost of revenue.
CB&I/Zachry/Chiyoda—We have a venture with Zachry and Chiyoda (CB&I—33.3% / Zachry—33.3% / Chiyoda—33.3%) to perform EPC work for an additional LNG liquefaction train at the aforementioned project site in Freeport, Texas. Our proportionate share of the venture project value is approximately $675,000.
CB&I/Chiyoda—We have a venture with Chiyoda (CB&I—50% / Chiyoda—50%) to perform EPC work for three LNG liquefaction trains in Hackberry, Louisiana. Our proportionate share of the venture project value is approximately $3,100,000.

14

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

The following table presents summarized balance sheet information for our proportionately consolidated ventures:
 
 
June 30, 2015
 
December 31, 2014
CB&I/Zachry
 
 
 
 
Current assets (1)
 
$
224,477

 
$
85,484

Current liabilities
 
$
290,437

 
$
149,891

CB&I/Zachry/Chiyoda
 
 
 
 
Current assets (1)
 
$
37,579

 
$

Current liabilities
 
$
41,197

 
$

CB&I/Chiyoda
 
 
 
 
Current assets (1)
 
$
194,680

 
$
102,035

Current liabilities
 
$
241,238

 
$
124,367

(1) 
Our venture arrangements allow for excess working capital of the ventures to be advanced to the venture partners. Such advances are returned to the venture for working capital needs as necessary. Accordingly, at a reporting period end a venture may have advances to its partners which are reflected as an advance receivable within current assets of the venture. At June 30, 2015 and December 31, 2014, other current assets on the Balance Sheet included approximately $193,600 and $71,200, respectively, related to our proportionate share of advances from the ventures to our venture partners. In addition, at June 30, 2015 and December 31, 2014 other current liabilities on the Balance Sheet included approximately $193,600 and $108,700, respectively, related to advances to CB&I from the ventures.
Equity Method Ventures—The following is a summary description of our significant unconsolidated joint ventures which have been accounted for using the equity method:
Chevron-Lummus Global (CLG)—We have a venture with Chevron (CB&I—50% / Chevron—50%), which provides licenses, engineering services and catalyst, primarily for the refining industry. As sufficient capital investments in CLG have been made by the venture partners, it does not qualify as a VIE. Additionally, we do not effectively control CLG and therefore do not consolidate the venture.
NET Power LLC (“NET Power”)—We have a venture with Exelon and 8 Rivers Capital (CB&I—33.3% / Exelon—33.3% / 8 Rivers Capital—33.3%), which was formed for the purpose of developing, commercializing and monetizing a new natural gas power system that produces zero atmospheric emissions, including carbon dioxide. NET Power is building a first-of-its-kind demonstration plant which will be funded by contributions and services from the venture partners and other parties. Our cash commitment for NET Power totals $47,300 and at June 30, 2015, we had made cumulative investments of approximately $13,100.
Consolidated Ventures—The following is a summary description of the significant joint ventures we consolidate due to their designation as VIEs for which we are the primary beneficiary:
CB&I/Kentz—We have a venture with Kentz (CB&I—65% / Kentz—35%) to perform the structural, mechanical, piping, electrical and instrumentation work on, and to provide commissioning support for, three LNG trains, including associated utilities and a gas processing and compression plant, for the Gorgon LNG project, located on Barrow Island, Australia. Our venture project value is approximately $5,000,000.
CB&I/AREVA—We have a venture with AREVA (CB&I52% / AREVA—48%) to design, license and construct a mixed oxide fuel fabrication facility in Aiken, South Carolina, which will be used to convert weapons-grade plutonium into fuel for nuclear power plants for the U.S. Department of Energy. Our venture project value is approximately $5,200,000.

15

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

The following table presents summarized balance sheet information for our consolidated VIEs:
 
 
June 30,
2015
 
December 31,
2014
CBI/Kentz
 
 
 
 
Current assets
 
$
196,484

 
$
220,930

Current liabilities
 
$
207,941

 
$
196,277

CBI/AREVA
 
 
 
 
Current assets
 
$
28,619

 
$
27,006

Current liabilities
 
$
70,159

 
$
73,124

All Other (1)
 
 
 
 
Current assets
 
$
115,409

 
$
130,458

Non-current assets
 
$
20,575

 
$
22,045

Total assets
 
$
135,984

 
$
152,503

Current liabilities
 
$
37,223

 
$
36,534

(1) 
Other ventures that we consolidate due to their designation as VIEs are not individually material to our financial results and are therefore aggregated as “All Other”.
Other—The use of these ventures exposes us to a number of risks, including the risk that our partners may be unable or unwilling to provide their share of capital investment to fund the operations of the venture or to complete their obligations to us, the venture, or ultimately, our customer. This could result in unanticipated costs to complete the projects, liquidated damages or contract disputes, including claims against our partners.
7. FACILITY REALIGNMENT LIABILITY
At June 30, 2015 and December 31, 2014, we had a facility realignment liability related to the recognition of future operating lease expense for vacated facility capacity where we remain contractually obligated to a lessor. The liability was recognized within other current and non-current liabilities, as applicable, based upon the anticipated timing of payments. The following table summarizes the movements in the facility realignment liability during the six months ended June 30, 2015:
 
 
Total
Balance at December 31, 2014
 
$
14,354

Charges
 
1,614

Cash payments
 
(5,169
)
Balance at June 30, 2015
 
$
10,799

8. DEBT
Our outstanding debt at June 30, 2015 and December 31, 2014 was as follows:
 
 
June 30,
2015
 
December 31,
2014
Current
 
 
 
 
Revolving facility and other short-term borrowings
 
$
596,740

 
$
164,741

Current maturities of long-term debt
 
131,096

 
105,997

Current debt
 
$
727,836

 
$
270,738

Long-Term
 
 
 
 
Term Loan: $1,000,000 term loan (interest at LIBOR plus an applicable floating margin)
 
$
775,000

 
$
825,000

Senior Notes: $800,000 senior notes, series A-D (fixed interest ranging from 4.15% to 5.30%)
 
800,000

 
800,000

Other long-term debt
 
42,181

 
45,155

Less: current maturities of long-term debt
 
(131,096
)
 
(105,997
)
Long-term debt
 
$
1,486,085

 
$
1,564,158


16

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

Committed Facilities—We have a five-year, $1,350,000, committed and unsecured revolving facility (the “Revolving Facility”) with Bank of America ("BofA"), as administrative agent, and BNP Paribas Securities Corp., BBVA Compass, Credit Agricole Corporate and Investment Bank (“Credit Agricole”) and The Royal Bank of Scotland plc, each as syndication agents, which expires in October 2018. The Revolving Facility has a $675,000 aggregate borrowing and financial letter of credit sublimit (with financial letters of credit not to exceed $270,000) and certain financial covenants, including a maximum leverage ratio of 3.00, a minimum fixed charge coverage ratio of 1.75, and a minimum net worth level calculated as $2,140,323 at June 30, 2015. The Revolving Facility also includes customary restrictions regarding subsidiary indebtedness, sales of assets, liens, investments, type of business conducted, and mergers and acquisitions, and includes a trailing twelve-month limitation of $250,000 for dividend payments and share repurchases if our leverage ratio exceeds 1.50 (unlimited if our leverage ratio is equal to or below 1.50), among other restrictions. In addition to interest on debt borrowings, we are assessed quarterly commitment fees on the unutilized portion of the facility as well as letter of credit fees on outstanding instruments. The interest, commitment fee, and letter of credit fee percentages are based upon our quarterly leverage ratio. In the event we borrow funds under the facility, interest is assessed at either prime plus an applicable floating margin (3.25% and 0.50%, respectively at June 30, 2015), or LIBOR plus an applicable floating margin (0.19% and 1.50%, respectively at June 30, 2015). At June 30, 2015, we had $300,000 of outstanding borrowings under the facility and $201,101 of outstanding letters of credit under the facility (none of which were financial letters of credit), providing $848,899 of available capacity, of which $375,000 may be utilized for borrowings. During the six months ended June 30, 2015, our weighted average interest rate on borrowings under the facility was approximately 1.8%, inclusive of the applicable floating margin.
Effective July 8, 2015, we amended the Revolving Facility to remove the borrowing sublimit. The amended facility maintains the $270,000 sublimit for financial letters of credit, and has financial and restrictive covenants similar to those of the previous facility.
We also have a five-year, $650,000, committed and unsecured revolving credit facility (the “Second Revolving Facility”) with BofA, as administrative agent, and Credit Agricole, as syndication agent, which expires in February 2018. The Second Revolving Facility, which supplements our Revolving Facility, has a $487,500 borrowing and financial letter of credit sublimit and includes financial and restrictive covenants similar to those noted above for the Revolving Facility. In addition to interest on debt borrowings, we are assessed quarterly commitment fees on the unutilized portion of the facility as well as letter of credit fees on outstanding instruments. The interest, commitment fee, and letter of credit fee percentages are based upon our quarterly leverage ratio. In the event we borrow funds under the facility, interest is assessed at either prime plus an applicable floating margin (3.25% and 0.50% at June 30, 2015), or LIBOR plus an applicable floating margin (0.19% and 1.50% at June 30, 2015). At June 30, 2015, we had $59,000 of outstanding borrowings and $19,529 of outstanding letters of credit under the facility (including $3,991 of financial letters of credit), providing $571,471 of available capacity, of which $424,509 may be utilized for borrowings. During the six months ended June 30, 2015, our weighted average interest rate on borrowings under the facility was approximately 3.8%, inclusive of the applicable floating margin.
Effective July 8, 2015, we amended and restated the Second Revolving Facility to increase the overall capacity to $800,000, extend the expiration date to July 8, 2020, remove the borrowing sublimit, and provide a financial letter of credit sublimit of $50,000. The amended facility has financial and restrictive covenants similar to those of the previous facility.
Uncommitted Facilities—We also have various short-term, uncommitted letter of credit and borrowing facilities (the "Uncommitted Facilities") across several geographic regions of approximately $3,575,908, of which $440,000 may be utilized for borrowings ($439,294 at June 30, 2015, net of letter of credit utilization of $706 under certain facilities). At June 30, 2015, we had $237,740 of outstanding borrowings and $1,207,918 of outstanding letters of credit under these facilities, providing $2,130,250 of available capacity, of which $201,554 may be utilized for borrowings. During the six months ended June 30, 2015, our weighted average interest rate on borrowings under the facility was approximately 1.2%.
Term Loan—At June 30, 2015, we had $775,000 outstanding on our four-year, $1,000,000 unsecured term loan (the "Term Loan") with BofA as administrative agent. Interest and principal under the Term Loan is payable quarterly in arrears and bears interest at LIBOR plus an applicable floating margin (0.19% and 1.50%, respectively at June 30, 2015). However, we continue to utilize an interest rate swap to hedge against $391,375 of the outstanding $775,000 Term Loan, which resulted in a weighted average interest rate of approximately 2.0% during the six months ended June 30, 2015, inclusive of the applicable floating margin. Future annual maturities for the Term Loan are $50,000, $150,000 and $575,000 for the remainder of 2015, 2016 and 2017, respectively. The Term Loan includes financial and restrictive covenants similar to those noted above for the Revolving Facility.
Effective July 8, 2015, we entered into a $500,000 term loan (the “Second Term Loan”). The Second Term Loan requires that $275,000 of the loan proceeds be utilized to prepay a portion of the 2017 principal due on the Term Loan. Thereafter, interest and principal under the Second Term Loan is payable quarterly in arrears beginning in June 2017 and bears interest at LIBOR plus an applicable floating margin (rates are equivalent to the Term Loan). Future annual maturities for the Second

17

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

Term Loan are $56,250, $75,000, $75,000 and $293,750 for 2017, 2018, 2019, and 2020, respectively. The Second Term Loan has financial and restrictive covenants similar to those of the Term Loan.
Senior Notes—We have a series of senior notes totaling $800,000 in the aggregate (the “Senior Notes”), with Merrill Lynch, Pierce, Fenner & Smith Incorporated, and Credit Agricole, as administrative agents. The Senior Notes have financial and restrictive covenants similar to those noted above for the Revolving Facility. The Senior Notes include Series A through D, which contain the following terms:
Series A—Interest due semi-annually at a fixed rate of 4.15%, with principal of $150,000 due in December 2017
Series B—Interest due semi-annually at a fixed rate of 4.57%, with principal of $225,000 due in December 2019
Series C—Interest due semi-annually at a fixed rate of 5.15%, with principal of $275,000 due in December 2022
Series D—Interest due semi-annually at a fixed rate of 5.30%, with principal of $150,000 due in December 2024
Effective July 22, 2015, we entered into a $200,000 note purchase and guarantee agreement (the "New Senior Note"). Interest is due semi-annually at a fixed rate of 4.53%, with principal of $200,000 due in July 2025. The New Senior Note has financial and restrictive covenants similar to those of the Senior Notes.
Other Long-Term Debt—At June 30, 2015, we also had $42,181 outstanding on a $48,081 six-year secured (construction equipment) term loan. Interest and principal under the loan is payable monthly in arrears and bears interest at 3.26%. Future annual maturities are $3,023, $6,196, $6,401, $6,613, $6,832 and $13,116 for the remainder of 2015, 2016, 2017, 2018, 2019 and 2020, respectively.
Compliance and Other—During the six months ended June 30, 2015, maximum outstanding borrowings under our revolving credit and other facilities were approximately $1,144,240. In addition to providing letters of credit, we also issue surety bonds in the ordinary course of business to support our contract performance. At June 30, 2015, we had $689,226 of outstanding surety bonds. At June 30, 2015, we were in compliance with all of our restrictive and financial covenants associated with our debt and revolving credit facilities. Capitalized interest was insignificant for the six months ended June 30, 2015 and 2014.
9. FINANCIAL INSTRUMENTS
Derivatives
Foreign Currency Exchange Rate Derivatives —At June 30, 2015, the notional value of our outstanding forward contracts to hedge certain foreign exchange-related operating exposures was approximately $51,400. These contracts vary in duration, maturing up to four years from period-end. We designate certain of these hedges as cash flow hedges and accordingly, changes in their fair value are recognized in AOCI until the associated underlying operating exposure impacts our earnings. We exclude forward points, which are recognized as ineffectiveness within cost of revenue and are not material to our earnings, from our hedge assessment analysis.
Interest Rate Derivatives—We continue to utilize a swap arrangement to hedge against interest rate variability associated with $391,375 of our outstanding $775,000 Term Loan. The swap arrangement has been designated as a cash flow hedge as its critical terms matched those of the Term Loan at inception and through June 30, 2015. Accordingly, changes in the fair value of the swap arrangement are recognized in AOCI until the associated underlying exposure impacts our earnings.
Financial Instruments Disclosures
Fair Value—Financial instruments are required to be categorized within a valuation hierarchy based upon the lowest level of input that is significant to the fair value measurement. The three levels of the valuation hierarchy are as follows:
Level 1—Fair value is based upon quoted prices in active markets.
Level 2—Fair value is based upon internally-developed models that use, as their basis, readily observable market parameters. Our derivative positions are classified within Level 2 of the valuation hierarchy as they are valued using quoted market prices for similar assets and liabilities in active markets. These level 2 derivatives are valued utilizing an income approach, which discounts future cash flow based upon current market expectations and adjusts for credit risk.
Level 3—Fair value is based upon internally-developed models that use, as their basis, significant unobservable market parameters. We did not have any Level 3 classifications at June 30, 2015 or December 31, 2014.

18

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

The following table presents the fair value of our foreign currency exchange rate derivatives and interest rate derivatives at June 30, 2015 and December 31, 2014, respectively, by valuation hierarchy and balance sheet classification:
 
June 30, 2015
 
December 31, 2014
 
Level 1
 
Level 2
 
Level 3
 
Total
 
Level 1
 
Level 2
 
Level 3
 
Total
Assets
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Derivatives (1)
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Other current assets
$

 
$
2,874

 
$

 
$
2,874

 
$

 
$
852

 
$

 
$
852

Other non-current assets

 
703

 

 
703

 

 
2,248

 

 
2,248

Total assets at fair value
$

 
$
3,577

 
$

 
$
3,577

 
$

 
$
3,100

 
$

 
$
3,100

Liabilities
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Derivatives
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Other current liabilities
$

 
$
(8,078
)
 
$

 
$
(8,078
)
 
$

 
$
(12,728
)
 
$

 
$
(12,728
)
Other non-current liabilities

 
(2,203
)
 

 
(2,203
)
 

 
(1,873
)
 

 
(1,873
)
Total liabilities at fair value
$

 
$
(10,281
)
 
$

 
$
(10,281
)
 
$

 
$
(14,601
)
 
$

 
$
(14,601
)
(1) 
We are exposed to credit risk on our hedging instruments associated with potential counterparty non-performance, and the fair value of our derivatives reflects this credit risk. The total level 2 assets at fair value above represent the maximum loss that we would incur on our outstanding hedges if the applicable counterparties failed to perform according to the hedge contracts. To help mitigate counterparty credit risk, we transact only with counterparties that are rated as investment grade or higher and monitor all counterparties on a continuous basis.
The carrying values of our cash and cash equivalents (primarily consisting of bank deposits), accounts receivable and accounts payable approximate their fair values because of the short-term nature of these instruments. At June 30, 2015, the fair value of our Term Loan, based upon the current market rates for debt with similar credit risk and maturity, approximated its carrying value as interest is based upon LIBOR plus an applicable floating margin. Our Senior Notes are categorized within level 2 of the valuation hierarchy and had a total fair value of approximately $774,200 and $785,100 at June 30, 2015 and December 31, 2014, respectively, based on the current market rates for debt with similar credit risk and maturities.
Derivatives Disclosures
Fair Value—The following table presents the total fair value by underlying risk and balance sheet classification for derivatives designated as cash flow hedges and derivatives not designated as cash flow hedges at June 30, 2015 and December 31, 2014:
 
 
Fair Value of Derivatives Classified as Other Current and Non-Current Assets on the Balance Sheet
 
Fair Value of Derivatives Classified as Other Current and Non-Current Liabilities on the Balance Sheet
 
 
June 30,
2015
 
December 31,
2014
 
June 30,
2015
 
December 31,
2014
Derivatives designated as cash flow hedges
 
 
 
 
 
 
 
 
Interest rate
 
$
674

 
$
2,258

 
$
(939
)
 
$
(1,229
)
Foreign currency
 
1,098

 
39

 
(2,622
)
 
(4,996
)
 
 
$
1,772

 
$
2,297

 
$
(3,561
)
 
$
(6,225
)
Derivatives not designated as cash flow hedges
 
 
 
 
 
 
 
 
Interest rate
 
$

 
$

 
$

 
$

Foreign currency
 
1,805

 
803

 
(6,720
)
 
(8,376
)
 
 
$
1,805

 
$
803

 
$
(6,720
)
 
$
(8,376
)
Total fair value
 
$
3,577

 
$
3,100

 
$
(10,281
)
 
$
(14,601
)

19

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

Master Netting Arrangements (MNAs)—Our derivatives are executed under International Swaps and Derivatives Association MNAs, which generally allow us and our counterparties to net settle, in a single net payable or receivable, obligations due on the same day, in the same currency and for the same type of derivative instrument. We have elected the option to record all derivatives on a gross basis in our Balance Sheet. The following table presents our derivative assets and liabilities at June 30, 2015 on a gross basis and a net settlement basis:
 
Gross
Amounts
Recognized
(i)
 
Gross Amounts
Offset on the
Balance Sheet
(ii)
 
Net Amounts
Presented on the
Balance Sheet
(iii) = (i) - (ii)
 
Gross Amounts Not Offset on
the Balance Sheet (iv)
 
Net Amount
(v) = (iii) - (iv)
 
Financial
Instruments
 
Cash
Collateral
Received
 
Derivatives
 
 
 
 
 
 
 
 
 
 
 
Assets:
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
674

 
$

 
$
674

 
$

 
$

 
$
674

Foreign currency
2,903

 

 
2,903

 
(293
)
 

 
2,610

Total assets
$
3,577

 
$

 
$
3,577

 
$
(293
)
 
$

 
$
3,284

Liabilities:
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
(939
)
 
$

 
$
(939
)
 
$

 
$

 
$
(939
)
Foreign currency
(9,342
)
 

 
(9,342
)
 
293

 

 
(9,049
)
Total liabilities
$
(10,281
)
 
$

 
$
(10,281
)
 
$
293

 
$

 
$
(9,988
)
AOCI/Other—The following table presents the total value, by underlying risk, recognized in other comprehensive income (“OCI”) and reclassified from AOCI to interest expense (interest rate derivatives) and cost of revenue (foreign currency derivatives) during the three and six months ended June 30, 2015 and 2014 for derivatives designated as cash flow hedges:
 
Amount of Gain (Loss) on Effective Derivative Portion
 
Recognized in OCI
 
Reclassified from AOCI into Earnings (1)
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
2015
 
2014
 
2015
 
2014
 
2015
 
2014
 
2015
 
2014
Derivatives designated as cash flow hedges
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Interest rate
$
(514
)
 
$
(1,689
)
 
$
(2,222
)
 
$
(2,191
)
 
$
(453
)
 
$
(546
)
 
$
(927
)
 
$
(1,089
)
Foreign currency
(285
)
 
19

 
(2,740
)
 
(47
)
 
(1,333
)
 
(113
)
 
(2,470
)
 
354

Total
$
(799
)
 
$
(1,670
)
 
$
(4,962
)
 
$
(2,238
)
 
$
(1,786
)
 
$
(659
)
 
$
(3,397
)
 
$
(735
)
(1) 
Net unrealized losses totaling $4,227 are anticipated to be reclassified from AOCI into earnings during the next 12 months due to settlement of the associated underlying obligations.
The following table presents the total value recognized in cost of revenue for the three and six months ended June 30, 2015 and 2014 for foreign currency derivatives not designated as cash flow hedges:
 
Amount of Gain (Loss) Recognized in Earnings
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
2015
 
2014
 
2015
 
2014
Derivatives not designated as cash flow hedges
 
 
 
 
 
 
 
Foreign currency
$
4,249

 
$
(7,716
)
 
$
(2,283
)
 
$
(6,210
)
Total
$
4,249

 
$
(7,716
)
 
$
(2,283
)
 
$
(6,210
)

20

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

10. RETIREMENT BENEFITS
Our 2014 Annual Report disclosed anticipated 2015 defined benefit pension and other postretirement plan contributions of $18,545 and $2,895, respectively. The following table provides updated contribution information for these plans at June 30, 2015:
 
Pension Plans
 
Other Postretirement Plans
Contributions made through June 30, 2015
$
10,302

 
$
1,233

Contributions expected for the remainder of 2015
6,770

 
1,233

Total contributions expected for 2015
$
17,072

 
$
2,466

The following table provides a breakout of the components of net periodic benefit cost associated with our defined benefit pension and other postretirement plans for the three and six months ended June 30, 2015 and 2014:
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
2015
 
2014
 
2015
 
2014
Pension Plans
 
 
 
 
 
 
 
Service cost
$
2,624

 
$
2,358

 
$
5,336

 
$
4,709

Interest cost
5,793

 
8,632

 
11,651

 
17,196

Expected return on plan assets
(7,069
)
 
(9,400
)
 
(14,206
)
 
(18,714
)
Amortization of prior service credits
(153
)
 
(121
)
 
(311
)
 
(241
)
Recognized net actuarial losses
1,904

 
1,193

 
3,838

 
2,374

Net periodic benefit cost
$
3,099

 
$
2,662

 
$
6,308

 
$
5,324

Other Postretirement Plans
 
 
 
 
 
 
 
Service cost
$
140

 
$
259

 
$
435

 
$
518

Interest cost
272

 
570

 
801

 
1,140

Recognized net actuarial gains
(1,115
)
 
(216
)
 
(1,265
)
 
(432
)
Net periodic benefit (income) cost
$
(703
)
 
$
613

 
$
(29
)
 
$
1,226

11. COMMITMENTS AND CONTINGENCIES
Legal Proceedings—We have been and may from time to time be named as a defendant in legal actions claiming damages in connection with engineering and construction projects, technology licenses, other services we provide, and other matters. These are typically claims that arise in the normal course of business, including employment-related claims and contractual disputes or claims for personal injury or property damage which occur in connection with services performed relating to project or construction sites. Contractual disputes normally involve claims relating to the timely completion of projects, performance of equipment or technologies, design or other engineering services or project construction services provided by us. We do not believe that any of our pending contractual, employment-related, personal injury or property damage claims and disputes will have a material adverse effect on our future results of operations, financial position or cash flow. See Note 14 for additional discussion of claims associated with our projects.
Asbestos Litigation—We are a defendant in lawsuits wherein plaintiffs allege exposure to asbestos due to work we may have performed at various locations. We have never been a manufacturer, distributor or supplier of asbestos products. Over the past several decades and through June 30, 2015, we have been named a defendant in lawsuits alleging exposure to asbestos involving approximately 5,800 plaintiffs and, of those claims, approximately 1,700 claims were pending and 4,100 have been closed through dismissals or settlements. Over the past several decades and through June 30, 2015, the claims alleging exposure to asbestos that have been resolved have been dismissed or settled for an average settlement amount of approximately two thousand dollars per claim. We review each case on its own merits and make accruals based upon the probability of loss and our estimates of the amount of liability and related expenses, if any. While we have seen an increase in the number of recent filings, especially in one specific venue, we do not believe that the increase or any unresolved asserted claims will have a material adverse effect on our future results of operations, financial position or cash flow, and at June 30, 2015, we had approximately $5,100 accrued for liability and related expenses. With respect to unasserted asbestos claims, we cannot identify a population of potential claimants with sufficient certainty to determine the probability of a loss and to make a reasonable estimate of liability, if any. While we continue to pursue recovery for recognized and unrecognized contingent losses through insurance, indemnification arrangements or other sources, we are unable to quantify the amount, if any, that we may expect to recover

21

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

because of the variability in coverage amounts, limitations and deductibles, or the viability of carriers, with respect to our insurance policies for the years in question.
Environmental Matters—Our operations are subject to extensive and changing U.S. federal, state and local laws and regulations, as well as the laws of other countries, that establish health and environmental quality standards. These standards, among others, relate to air and water pollutants and the management and disposal of hazardous substances and wastes. We are exposed to potential liability for personal injury or property damage caused by any release, spill, exposure or other accident involving such pollutants, substances or wastes.
In connection with the historical operation of our facilities, including those associated with acquired operations, substances which currently are or might be considered hazardous were used or disposed of at some sites that will or may require us to make expenditures for remediation. In addition, we have agreed to indemnify parties from whom we have purchased or to whom we have sold facilities for certain environmental liabilities arising from acts occurring before the dates those facilities were transferred.
We believe we are in compliance, in all material respects, with environmental laws and regulations and maintain insurance coverage to mitigate our exposure to environmental liabilities. We do not believe any environmental matters will have a material adverse effect on our future results of operations, financial position or cash flow. We do not anticipate we will incur material capital expenditures for environmental controls or for the investigation or remediation of environmental conditions during the remainder of 2015 or 2016.
12. ACCUMULATED OTHER COMPREHENSIVE INCOME
The following table presents changes in AOCI, net of tax, by component, and reclassification of AOCI into earnings, net of tax, for each component, during the six months ended June 30, 2015:
 
 
Six Months Ended June 30, 2015
 
 
Currency
Translation
Adjustment
(1)
 
Unrealized
Fair Value Of
Cash Flow Hedges
 
Defined Benefit
Pension and Other
Postretirement Plans
 
Total
Balance at December 31, 2014
 
$
(133,787
)
 
$
(2,713
)
 
$
(125,897
)
 
$
(262,397
)
OCI before reclassifications
 
(35,004
)
 
(2,568
)
 
7,610

 
(29,962
)
Amounts reclassified from AOCI
 

 
2,488

 
1,869

 
4,357

Net OCI
 
(35,004
)
 
(80
)
 
9,479

 
(25,605
)
Balance at June 30, 2015
 
$
(168,791
)
 
$
(2,793
)
 
$
(116,418
)
 
$
(288,002
)
(1) 
During the six months ended June 30, 2015, the currency translation adjustment component of AOCI was unfavorably impacted primarily by movements in the Australian Dollar and Euro exchange rates against the U.S. Dollar.
 
 
Amount Reclassified From AOCI
AOCI Components
 
Unrealized Fair Value Of Cash Flow Hedges (1)
 
 
Interest rate derivatives (interest expense)
 
$
927

Foreign currency derivatives (cost of revenue)
 
2,470

Total, before taxes
 
3,397

Taxes
 
(909
)
Total, net of taxes
 
$
2,488

Defined Benefit Pension and Other Postretirement Plans (2)
 
 
Amortization of prior service credits
 
$
(311
)
Recognized net actuarial losses
 
2,573

Total, before taxes
 
2,262

Taxes
 
(393
)
Total, net of taxes
 
$
1,869

(1) 
See Note 9 for further discussion of our cash flow hedges, including the total value reclassified from AOCI to earnings.
(2) 
See Note 10 for further discussion of our defined benefit and other postretirement plans, including the components of net periodic benefit cost.

22

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

13. EQUITY-BASED INCENTIVE PLANS
Under our equity-based incentive plans, we can issue shares to employees and directors in the form of restricted stock units (“RSUs”), performance shares and stock options. Changes in common stock, additional paid-in capital and treasury stock during the six months ended June 30, 2015 and 2014 primarily related to activity associated with the equity-based incentive plans and share repurchases. At June 30, 2015 and December 31, 2014, and for the six months ended June 30, 2015 and 2014, cash-settled equity-based awards, including RSUs and stock appreciation rights, were not material.
During the six months ended June 30, 2015, we granted the following awards associated with our equity-based incentive plans:
 
Shares (1)
 
Weighted Average
Grant-Date Fair
Value Per Share
RSUs
979

 
$
42.35

Performance shares
832

 
$
41.24

Total
1,811

 
 
(1) 
No stock options were granted during the six months ended June 30, 2015.
During the six months ended June 30, 2015, we had the following activity associated with our equity-based incentive plans and employee stock purchase plan (“ESPP”):
 
Shares
Performance shares (issued upon vesting)
563

RSUs (issued upon vesting)
409

Stock options (issued upon exercise)
49

ESPP shares (issued upon sale)
250

Total shares issued
1,271

During the three months ended June 30, 2015 and 2014, we recognized $7,100 and $8,469, respectively, of stock-based compensation expense, and during the six months ended June 30, 2015 and 2014, we recognized $39,063 and $51,534, respectively, of stock-based compensation expense, primarily within selling and administrative expense.
During the six months ended June 30, 2015, we repurchased 339 shares for $13,887 (an average price of $40.96), including $12,492 to purchase 297 shares for taxes withheld on taxable share distributions and $1,395 to purchase 42 shares of our outstanding common stock.
14. UNAPPROVED CHANGE ORDERS, CLAIMS, INCENTIVES AND OTHER CONTRACT RECOVERIES
We recognize revenue associated with unapproved change orders and claims to the extent the related costs have been incurred, the value can be reliably estimated and recovery is probable, and we recognize revenue associated with incentive fees when the value can be reliably estimated and recovery is probable. In addition, we include in contract price amounts contractually recoverable from our customers and consortium partners.
Nuclear Projects—We have consortium agreements (the “Consortium Agreements”) with Westinghouse Electric Company ("WEC") under which we have contracted with two separate customers (the “Customer Contracts”) for the construction of two nuclear power plants in Georgia (the “Georgia Nuclear Project”) and South Carolina (the "South Carolina Nuclear Project") (collectively, the “Nuclear Projects”). The results of the Nuclear Projects are reflected within our Engineering & Construction and Fabrication Services operating groups. Under the scope of work provided in each of the Consortium Agreements, WEC is primarily responsible for engineering and procurement activities associated with the nuclear island component of the Nuclear Projects, while we are responsible for engineering, procurement and fabrication for the balance of plant and substantially all of the construction activities for the Nuclear Projects. The Customer Contracts provide WEC and us contractual entitlement (“Customer Obligation(s)”) for recovery of certain estimated costs in excess of contractually stipulated amounts. In addition to the aforementioned protections for us under the Customer Contracts, the Consortium Agreements also provide contractual entitlement for us to recover from WEC (“WEC Obligation(s)”) certain estimated costs in excess of contractually stipulated amounts, to the extent not recoverable from our customers. Project price for the Nuclear Projects includes estimated amounts recoverable under the aforementioned Customer Obligations and WEC Obligations.
At June 30, 2015 and December 31, 2014, we also had approximately $838,600 of unapproved change orders and claims included in project price related to claims with our customer for the Georgia Nuclear Project resulting from increased

23

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

engineering, equipment supply, material and fabrication and construction costs resulting from regulatory-required design changes and delays in our customer’s obtaining the combined operating license (“COL”) for the project. Specifically, we have entered into a formal dispute resolution process on certain claims associated with the shield building, large structural modules and COL issuance delays. To the extent we are unsuccessful recovering these amounts from our customer, the amounts are contractually recoverable under the aforementioned WEC Obligations.
At June 30, 2015 and December 31, 2014, we also had approximately $442,000 and $373,000 of unapproved change orders and claims, respectively, included in project price related to a portion of the forecast cost impacts for the South Carolina Nuclear Project associated with extensions of schedule.
Through June 30, 2015, approximately $431,000 had been recognized as revenue on a cumulative POC basis related to the unapproved change orders and claims for the Nuclear Projects. Although we have not reached resolution on the aforementioned matters, at June 30, 2015, we had received contractually required partial payments totaling approximately $210,000.
We believe the amounts included in project price related to the unapproved change orders and claims, and the Customer Obligations and WEC Obligations, are recoverable under the aforementioned provisions of our contractual arrangements and reflect our best estimate of recovery amounts. The Nuclear Projects have long construction durations and the cost estimates cover costs that will be incurred over several years. It is anticipated that these commercial matters may not be resolved in the near term. If we do not resolve these matters for the amounts recorded, or to the extent we are not successful in recovering amounts contractually due under the Customer Obligations or WEC Obligations, or to the extent there are future cost increases on the Nuclear Projects that we cannot recover under either the Customer Obligations or WEC Obligations, it could have an adverse effect on our results of operations, financial position and cash flow.
Other—At June 30, 2015 and December 31, 2014, we had additional unapproved change orders and claims included in project price totaling approximately $107,000 and $98,100, respectively, for other projects primarily within our Engineering & Construction and Fabrication Services operating groups. We also had incentives included in project price of approximately $35,000 and $32,600 at June 30, 2015 and December 31, 2014, respectively, for projects in our Engineering & Construction and Capital Services operating groups. Of these aforementioned amounts, approximately $113,000 had been recognized as revenue on a cumulative POC basis through June 30, 2015.
The aforementioned amounts recorded in project price and receivables reflect our best estimate of recovery amounts; however, the ultimate resolution and amounts received could differ from these estimates and could have a material adverse effect on our results of operations, financial position and cash flow.
15. SEGMENT INFORMATION
Our management structure and internal and public segment reporting are aligned based upon the services offered by our four operating groups, which represent our reportable segments. As discussed in Note 1 and 2, during the three months ended March 31, 2015, we realigned our four operating groups to reflect the present management oversight of our operations. Our maintenance business that was previously reported within our Engineering & Construction operating group (formerly Engineering, Construction & Maintenance) is now reported within our Capital Services operating group (formerly Environmental Solutions), and our engineered products business that was previously reported within our Technology operating group is now reported within our Fabrication Services operating group. The segment results for the three and six months ended June 30, 2014 were reclassified to conform to the 2015 presentation. The following provides a description of our realigned operating groups:
Engineering & Construction—Engineering & Construction provides EPC services for major energy infrastructure facilities.
Fabrication Services—Fabrication Services provides fabrication of piping systems, process and nuclear modules; fabrication and erection of steel plate structures; manufacturing and distribution of pipe and fittings; and engineered products for the oil and gas, petrochemicals, water and wastewater, mining, mineral processing and power generation industries.
Technology—Technology provides licensed process technologies and catalysts for use in petrochemical facilities and oil refineries, and offers process planning and project development services and a comprehensive program of aftermarket support. Technology also has a 50% owned unconsolidated CLG joint venture that provides licensed technologies, engineering services and catalyst, primarily for the refining industry.
Capital Services—Capital Services provides comprehensive maintenance services, environmental engineering and remediation, infrastructure EPC services, program management, and disaster response and recovery for private sector customers and governments.

24

Table of Contents
Chicago Bridge & Iron Company N.V.
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS — (Continued)

Our Chief Executive Officer evaluates the performance of the aforementioned operating groups based upon revenue and income from operations. Each operating group's income from operations reflects corporate costs, allocated based primarily upon revenue. Intersegment revenue is netted against the revenue of the segment receiving the intersegment services. For the three months ended June 30, 2015 and 2014, intersegment revenue totaled approximately $107,500 and $114,800, respectively, and for the six months ended June 30, 2015 and 2014, intersegment revenue totaled approximately $223,200 and $228,700, respectively. Intersegment revenue for the aforementioned periods primarily related to services provided by our Fabrication Services operating group to our Engineering & Construction operating group.
The following table presents revenue and income from operations by reportable segment for the three and six months ended June 30, 2015 and 2014:
 
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
 
2015
 
2014
 
2015
 
2014
Revenue
 
 
 
 
 
 
 
 
Engineering & Construction
 
$
1,916,122

 
$
1,939,898

 
$
3,734,708

 
$
3,626,079

Fabrication Services
 
611,330

 
694,295

 
1,249,139

 
1,366,206

Technology
 
92,975

 
102,387

 
192,336

 
204,960

Capital Services
 
586,686

 
557,799

 
1,156,675

 
1,025,266

Total revenue
 
$
3,207,113

 
$
3,294,379

 
$
6,332,858

 
$
6,222,511

Income From Operations 
 
 
 
 
 
 
 
 
Engineering & Construction
 
$
176,467

 
$
132,648

 
$
312,885

 
$
217,284

Fabrication Services
 
55,937

 
78,267

 
108,336

 
125,182

Technology
 
36,741

 
37,242

 
84,765

 
71,911

Capital Services
 
14,962

 
21,591

 
24,919

 
25,921

Total operating groups
 
284,107

 
269,748

 
530,905

 
440,298

Integration related costs
 

 
(9,537
)
 

 
(17,604
)
Total income from operations
 
$
284,107

 
$
260,211

 
$
530,905

 
$
422,694

In conjunction with the aforementioned realignment of our operating groups during the three months ended March 31, 2015, our total assets by reportable segment changed significantly, including an allocation of goodwill among our new and realigned reporting units based on the relative fair value of the reporting units being realigned. At June 30, 2015 and December 31, 2014, our total assets by reportable segment were as follows (with December 31, 2014 balances reflecting the realignment of our operating groups to conform with the 2015 presentation):
 
 
June 30,
2015
 
December 31,
2014
Assets
 
 
 
 
Engineering & Construction
 
$
5,492,825

 
$
4,555,703

Fabrication Services
 
2,202,043

 
2,229,346

Technology
 
894,196

 
837,445

Capital Services
 
1,697,798

 
1,758,537

Total assets
 
$
10,286,862

 
$
9,381,031

16. SUBSEQUENT EVENTS
Effective July 8, 2015, we entered into a Second Term Loan and amended our Revolving Facility and Second Revolving Facility. Effective July 22, 2015, we entered into a New Senior Note. For further discussion, see Note 8 to our Financial Statements.


25

Table of Contents

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations
The following “Management’s Discussion and Analysis of Financial Condition and Results of Operations” is provided to assist readers in understanding our financial performance during the periods presented and significant trends that may impact our future performance. This discussion should be read in conjunction with our Financial Statements and the related notes thereto.
OVERVIEW
General—We provide a wide range of services through our four operating groups, including conceptual design, technology, engineering, procurement, fabrication, modularization, construction, commissioning, maintenance, program management and environmental services to customers in the energy infrastructure market throughout the world, and are a provider of diversified government services. As discussed in Note 15 to our Financial Statements, during the first quarter 2015, we realigned our four operating groups to reflect the present management oversight of our operations. Our maintenance business that was previously reported within our Engineering & Construction operating group (formerly Engineering, Construction & Maintenance) is now reported within our Capital Services operating group (formerly Environmental Solutions), and our engineered products business that was previously reported within our Technology operating group is now reported within our Fabrication Services operating group. Our realigned operating groups, which represent our reportable segments, include: Engineering & Construction; Fabrication Services; Technology; and Capital Services. The segment results for the three and six months ended June 30, 2014 were reclassified to conform to our 2015 presentation.
We continue to be broadly diversified across the global energy infrastructure market. Our geographic diversity is illustrated by approximately 40% of our year to date 2015 revenue coming from projects outside the U.S. and approximately 15% of our June 30, 2015 backlog of approximately $29.4 billion being comprised of projects outside the U.S. The geographic mix of our revenue will evolve consistent with changes in our backlog mix, as well as shifts in future global energy demand. Our diversity in energy infrastructure end-markets ranges from upstream activities such as offshore oil and gas and onshore oil sands projects, to downstream activities such as gas processing, LNG, refining, and petrochemicals, to fossil and nuclear-based power plants. Planned investments across the natural gas value chain, including LNG and petrochemicals, remain strong, and we anticipate additional benefits from continued investments in U.S. shale gas. Global investments in power and petrochemical facilities are expected to continue, as are investments in various types of facilities which require storage structures and pre-fabricated pipe.
Our long-term contracts are awarded on a competitively bid and negotiated basis using a range of contracting options, including cost-reimbursable, fixed-price and hybrid, which has both cost-reimbursable and fixed-price characteristics. Under cost-reimbursable contracts, we generally perform our services in exchange for a price that consists of reimbursement of all customer-approved costs and a profit component, which is typically a fixed rate per hour, an overall fixed fee or a percentage of total reimbursable costs. Under fixed-price contracts, we perform our services and execute our projects at an established price. The timing of our revenue recognition may be impacted by the contracting structure of our contracts. Cost-reimbursable contracts, and hybrid contracts with a more significant cost-reimbursable component, generally provide our customers with greater influence over the timing of when we perform our work, and accordingly, such contracts often result in less predictability with respect to the timing of our revenue. Fixed-price contracts, and hybrid contracts with a more significant fixed-price component, tend to provide us with greater control over project schedule and the timing of when work is performed and costs are incurred, and accordingly, when revenue is recognized. Our shorter-term contracts and services are generally provided on a cost-reimbursable, fixed-price or unit price basis. Our June 30, 2015 backlog distribution by contracting type is described below within our operating group discussion.
Backlog for each of our operating groups generally consists of several hundred contracts, which are being executed globally. These contracts vary in size from less than one hundred thousand dollars in contract value to several billion dollars, with varying durations that can exceed five years. The differing types, sizes, and durations of our contracts, combined with their geographic diversity and stages of completion, often results in fluctuations in our quarterly operating group results as a percentage of operating group revenue. In addition, the relative contribution of each of our operating groups, and selling and administrative expense fluctuations, will impact our quarterly consolidated results as a percentage of consolidated revenue. Selling and administrative expense fluctuations are primarily impacted by our stock-based compensation costs, which are recognized predominantly in the first quarter each year due to the timing of stock awards and the immediate expensing of awards for participants that are eligible to retire. Although quarterly variability is not unusual in our business, we are currently not aware of any fundamental change in our backlog or business that would give rise to future operating results that would be significantly different from our recent historical norms.

26

Table of Contents

Engineering & Construction—Our Engineering & Construction operating group provides EPC services for major energy infrastructure facilities. As discussed above, the results for our maintenance business that were previously reported within our Engineering & Construction operating group are now reported within our Capital Services operating group.
Backlog for our Engineering & Construction operating group comprised approximately $19.9 billion (68%) of our consolidated June 30, 2015 backlog. The backlog composition by end market was approximately 50% power, 40% LNG, 5% refining, and 5% gas processing, petrochemical, oil sands and other end markets. Our power backlog was primarily concentrated in the U.S. and we anticipate that our significant future opportunities will be derived from both China and North America. Our LNG backlog was primarily concentrated in the Asia Pacific and North American regions and we anticipate significant opportunities will continue to be derived from these regions in addition to Africa. The majority of our refining-related backlog was derived from South America and we anticipate that our future opportunities will be derived from the Middle East, South America, Russia, and the Asia Pacific region. Our gas processing projects were primarily concentrated in the U.S. and the Asia Pacific region, where we anticipate continued strength. Our June 30, 2015 backlog distribution for this operating group by contracting type was approximately 85% fixed-price and hybrid and 15% cost-reimbursable.
Fabrication Services—Our Fabrication Services operating group provides fabrication of piping systems, process and nuclear modules; fabrication and erection of steel plate structures; manufacturing and distribution of pipe and fittings; and engineered products for the oil and gas, petrochemicals, water and wastewater, mining, mineral processing and power generation industries. As discussed above, the results for our engineered products business that were previously reported within our Technology operating group are now reported within our Fabrication Services operating group.
Backlog for our Fabrication Services operating group comprised approximately $3.2 billion (11%) of our consolidated June 30, 2015 backlog. The backlog composition by end market was approximately 40% petrochemical, 20% LNG (including low temp and cryogenic), 20% power, 10% refining, 5% gas processing and 5% other end markets. Our June 30, 2015 backlog distribution for this operating group by contracting type was approximately 95% fixed-price, hybrid, or unit based, with the remainder being cost-reimbursable.
Technology—Our Technology operating group provides licensed process technologies and catalysts for use in petrochemical facilities and oil refineries, and offers process planning and project development services and a comprehensive program of aftermarket support. Technology also has a 50% owned unconsolidated CLG joint venture that provides licensed technologies, engineering services and catalyst, primarily for the refining industry. As discussed above, the results for our engineered products business that were previously reported within our Technology operating group are now reported within our Fabrication Services operating group.
Backlog for our Technology operating group comprised approximately $541.9 million (2%) of our consolidated June 30, 2015 backlog and was primarily comprised of fixed-price contracts. Technology’s backlog excludes contracts related to our unconsolidated CLG joint venture, for which income is recognized as equity earnings.
Capital Services—Our Capital Services operating group provides comprehensive maintenance services, environmental engineering and remediation, infrastructure EPC services, program management, and disaster response and recovery for private sector customers and governments. As discussed above, the results for our maintenance business that were previously reported within our Engineering & Construction operating group are now reported within our Capital Services operating group.
Backlog for our Capital Services operating group comprised approximately $5.7 billion (19%) of our consolidated June 30, 2015 backlog. The backlog composition by end market was approximately 65% operations and maintenance services, 15% environmental services, 10% construction services and 10% program and project management, and was primarily concentrated in the U.S. Our June 30, 2015 backlog distribution for this operating group by contracting type was approximately 80% cost-reimbursable and 20% fixed-price.

27

Table of Contents

RESULTS OF OPERATIONS
Our new awards, revenue and income from operations by reportable segment were as follows:
 
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
 
(In thousands)
 
 
2015
 
% of
Total
 
2014
 
% of
Total
 
2015
 
% of
Total
 
2014
 
% of
Total
New Awards
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Engineering & Construction
 
$
1,305,951

 
46%
 
$
2,056,812

 
49%
 
$
2,515,358

 
43%
 
$
6,551,649

 
66%
Fabrication Services
 
844,715

 
30%
 
564,388

 
13%
 
1,772,089

 
30%
 
1,081,117

 
11%
Technology
 
81,087

 
3%
 
152,397

 
4%
 
158,109

 
3%
 
229,843

 
2%
Capital Services
 
612,763

 
21%
 
1,429,480

 
34%
 
1,430,143

 
24%
 
2,137,957

 
21%
Total new awards
 
$
2,844,516

 
 
 
$
4,203,077

 
 
 
$
5,875,699

 
 
 
$
10,000,566

 
 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
2015
 
% of
Total
 
2014
 
% of
Total
 
2015
 
% of
Total
 
2014
 
% of
Total
Revenue
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Engineering & Construction
 
$
1,916,122

 
60%
 
$
1,939,898

 
59%
 
$
3,734,708

 
59%
 
$
3,626,079

 
58%
Fabrication Services
 
611,330

 
19%
 
694,295

 
21%
 
1,249,139

 
20%
 
1,366,206

 
22%
Technology
 
92,975

 
3%
 
102,387

 
3%
 
192,336

 
3%
 
204,960

 
3%
Capital Services
 
586,686

 
18%
 
557,799

 
17%
 
1,156,675

 
18%
 
1,025,266

 
17%
Total revenue
 
$
3,207,113

 
 
 
$
3,294,379

 
 
 
$
6,332,858

 
 
 
$
6,222,511

 
 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
2015
 
% of
Revenue
 
2014
 
% of
Revenue
 
2015
 
% of
Revenue
 
2014
 
% of
Revenue
Income From Operations
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Engineering & Construction
 
$
176,467

 
9.2%
 
$
132,648

 
6.8%
 
$
312,885

 
8.4%
 
$
217,284

 
6.0%
Fabrication Services
 
55,937

 
9.2%
 
78,267

 
11.3%
 
108,336

 
8.7%
 
125,182

 
9.2%
Technology
 
36,741

 
39.5%
 
37,242

 
36.4%
 
84,765

 
44.1%
 
71,911

 
35.1%
Capital Services
 
14,962

 
2.6%
 
21,591

 
3.9%
 
24,919

 
2.2%
 
25,921

 
2.5%
Total operating groups
 
284,107

 
8.9%
 
269,748

 
8.2%
 
530,905

 
8.4%
 
440,298

 
7.1%
Integration related costs
 

 
 
 
(9,537
)
 
 
 

 
 
 
(17,604
)
 
 
Total income from operations
 
$
284,107

 
8.9%
 
$
260,211

 
7.9%
 
$
530,905

 
8.4%
 
$
422,694

 
6.8%
Consolidated Results
New Awards/Backlog—New awards represent the value of new contract commitments received during a given period, as well as scope growth on existing commitments, and are included in backlog until work is performed and revenue is recognized, or until cancellation. Our new awards may vary significantly each reporting period based upon the timing of our major new contract commitments.
New awards were $2.8 billion for the second quarter 2015, compared with $4.2 billion for the corresponding 2014 period. Significant new awards for the second quarter 2015 included a combined cycle gas turbine power project in the U.S. (approximately $600.0 million) within our Engineering & Construction operating group and scope increases for our large nuclear projects in the U.S. (approximately $600.0 million, including contractual entitlements, unapproved change orders and claims discussed further in Note 14 to our Financial Statements) for our Engineering & Construction and Fabrication Services operating groups. Significant new awards for the second quarter 2014 included scope increases for our existing refinery project in Colombia and LNG mechanical erection project in the Asia Pacific region (approximately $1.3 billion combined) and a combined cycle gas turbine power project in the U.S. (approximately $500.0 million), all within our Engineering & Construction operating group; and a nuclear power plant services award in the U.S. (approximately $800.0 million) within our Capital Services operating group. New awards for the first six months of 2015 were $5.9 billion, compared with $10.0 billion for the corresponding 2014 period. The decrease for the year-to-date 2015 period relative to the 2014 period was primarily due to the second quarter 2014 awards discussed above and significant first quarter 2014 awards, including our proportionate share of a $6.2 billion LNG export facility award in the U.S. (approximately $3.1 billion). See Operating Group Results below for further discussion.

28

Table of Contents

Backlog at June 30, 2015 was approximately $29.4 billion, compared to $30.4 billion at December 31, 2014, reflecting the impact of revenue exceeding new awards by $457.2 million and other adjustments, primarily related to foreign currency fluctuations associated with the strengthening of the U.S. Dollar against the Australian Dollar, Euro, Colombian Peso and Canadian Dollar. As noted in the Revenue and Gross Profit sections below, foreign currency fluctuations also had an unfavorable impact on our operating results for the second quarter and year-to-date 2015 periods.
Certain contracts within our Capital Services and Engineering & Construction operating groups are dependent upon funding from the U.S. government, where funds are appropriated on a year-by-year basis, while contract performance may take more than one year. Approximately $903.0 million of our backlog at June 30, 2015 for these operating groups was for contractual commitments that are subject to future funding decisions.
Revenue—Revenue was $3.2 billion for the second quarter 2015, representing a decrease of $87.3 million (3%) from the corresponding 2014 period. Revenue was $6.3 billion for the first six months of 2015, representing an increase of $110.3 million (2%) from the corresponding 2014 period. The decrease for the second quarter 2015 was primarily due to the wind down of various tank projects in Australia within our Fabrication Services operating group and a decrease in revenue on our cost reimbursable LNG mechanical erection and gas processing projects in the Asia Pacific region and refinery project in Colombia, partly offset by progress on our large U.S. nuclear projects and increased LNG revenue in the U.S. within our Engineering & Construction operating group. The increase for the first six months of 2015 was due to our first quarter also benefiting from increased progress on our large U.S. nuclear projects and LNG revenue in the U.S. within our Engineering & Construction operating group, and increased plant maintenance revenue within our Capital Services operating group, offset partly by the aforementioned second quarter impacts. Our second quarter and year-to-date 2015 revenue were unfavorably impacted relative to the 2014 periods by approximately $240.0 million and $390.0 million, respectively, due to foreign currency fluctuations associated with the strengthening of the U.S. Dollar against the Australian Dollar, British Pound, Canadian Dollar, Colombian Peso and Euro, primarily within our Engineering & Construction operating group. See Operating Group Results below for further discussion.
    Gross Profit—Gross profit was $383.1 million (11.9% of revenue) for the second quarter 2015, compared with $381.2 million (11.6% of revenue) for the corresponding 2014 period. Gross profit for the first six months of 2015 was $753.3 million (11.9% of revenue), compared with $682.6 million (11.0% of revenue) for the corresponding 2014 period. The increase as a percentage of revenue for the second quarter 2015 was primarily attributable to higher margin backlog. The increase in absolute dollars and as a percentage of revenue for the year-to-date 2015 period was primarily attributable to our higher revenue volume, higher margin backlog and leverage of operating costs. Our second quarter and year-to-date 2015 gross profit were unfavorably impacted relative to the 2014 periods by approximately $26.0 million and $40.0 million, respectively, due to lower revenue volume resulting from foreign currency fluctuations associated with the strengthening of the U.S. Dollar, primarily within our Engineering & Construction operating group, as noted in the Revenue section above.
Selling and Administrative Expense—Selling and administrative expense was $85.2 million (2.7% of revenue) for the second quarter 2015, compared with $98.0 million (3.0% of revenue) for the corresponding 2014 period. Selling and administrative expense for the first six months of 2015 was $194.3 million (3.1% of revenue), compared with $217.2 million (3.5% of revenue) for the corresponding 2014 period. The decreases in absolute dollars and as a percentage of revenue were primarily attributable to lower incentive plan costs (approximately $9.0 million and $17.0 million for the second quarter and year-to-date periods, respectively) and our cost reduction initiatives. Our stock-based compensation costs, which are predominantly in selling and administrative expense, are higher in the first quarter each year due to the immediate expensing of awards for those participants that are eligible to retire. Stock-based compensation expense totaled approximately $39.1 million and $51.5 million for the first six months of 2015 and 2014, respectively, or 63% and 76% of estimated annual expense for each of the respective periods.
Intangibles Amortization—Intangibles amortization was $14.9 million and $30.6 million for the second quarter and first six months of 2015, respectively, compared with $16.8 million and $33.1 million for the corresponding 2014 periods. The decreases relative to the 2014 periods were primarily attributable to intangible assets that became fully amortized during the first quarter 2015 and the impact of foreign currency translation.
Equity Earnings—Equity earnings were $0.4 million and $4.6 million for the second quarter and first six months of 2015, respectively, compared with $3.2 million and $7.3 million for the corresponding 2014 periods and were primarily associated with our unconsolidated CLG joint venture.
Other Operating Expense (Income), Net—Other operating expense (income), net, generally represents losses (gains) associated with the sale or disposition of property and equipment. For the first six months of 2015, other operating expense (income), net also included a gain of approximately $7.5 million related to the contribution of a technology to our unconsolidated CLG joint venture and a foreign exchange loss of approximately $11.0 million associated with the re-measurement of certain non-U.S. Dollar denominated net assets, both of which occurred during the first quarter 2015.

29

Table of Contents

Integration Related Costs—Integration related costs were $9.5 million and $17.6 million for the second quarter and first six months of 2014, respectively, and primarily related to facility consolidations, including the associated accrued future lease costs for vacated facilities and unutilized capacity, personnel relocation and severance related costs, and systems integration costs.
Income from Operations—Income from operations was $284.1 million (8.9% of revenue) for the second quarter 2015, compared with $260.2 million (7.9% of revenue) for the corresponding 2014 period. Income from operations for the first six months of 2015 was $530.9 million (8.4% of revenue), compared with $422.7 million (6.8% of revenue) for the corresponding 2014 period. The changes in absolute dollars and percentages of revenue for the three and six-month periods were primarily attributable to the reasons noted above. See Operating Group Results below for further discussion.
Interest Expense and Interest Income—Interest expense was $21.1 million for the second quarter 2015, compared with $21.7 million for the corresponding 2014 period. Interest expense for the first six months of 2015 was $43.4 million, compared with $40.6 million for the corresponding 2014 period. The second quarter and year-to-date 2015 periods were impacted by higher average revolving credit facility and other borrowings, offset by a decrease during the second quarter 2015 due to the reversal of accrued interest (approximately $1.3 million) associated with the resolution of uncertain tax positions. Interest income was $2.2 million for the second quarter 2015, compared with $1.5 million for the corresponding 2014 period. Interest income for the first six months of 2015 was $4.2 million, compared with $3.5 million for the corresponding 2014 period.
Income Tax Expense—Income tax expense for the second quarter 2015 was $79.3 million (29.9% of pre-tax income), compared with $72.9 million (30.4% of pre-tax income) for the corresponding 2014 period. Income tax expense for the first six months of 2015 was $149.1 million (30.3% of pre-tax income), compared with $115.9 million (30.0% of pre-tax income) for the corresponding 2014 period. Our second quarter and year-to-date 2015 tax rate increased compared to the corresponding periods due to anticipated increased full-year pre-tax income in higher tax rate jurisdictions, primarily the U.S. (approximately 1.0% for both the second quarter and year-to-date periods). In addition to the aforementioned, our second quarter 2015 tax rate benefited from the impact of previously unrecognized tax benefits and other adjustments recorded during the period (approximately 1.5%). Our year-to-date 2015 and 2014 tax rates also benefited from previously unrecognized tax benefits and other adjustments recorded during the respective periods (approximately 2.0% and 1.0%, respectively). Our tax rate may continue to experience fluctuations due primarily to changes in the geographic distribution of our pre-tax income.
Net Income Attributable to Noncontrolling Interests—Noncontrolling interests are primarily associated with our large LNG mechanical erection project in the Asia Pacific region and certain operations in the U.S. and Middle East. The 2014 period also included our large gas processing project in the Asia Pacific region. Net income attributable to noncontrolling interests was $16.4 million for the second quarter 2015, compared with $24.7 million for the corresponding 2014 period. Net income attributable to noncontrolling interests was $40.9 million for the first six months of 2015, compared with $38.5 million for the corresponding 2014 period. The changes compared to the 2014 periods were commensurate with the level of applicable operating results for the aforementioned projects and operations.
Operating Group Results
Engineering & Construction
New Awards—New awards were $1.3 billion for the second quarter 2015, compared with $2.1 billion for the corresponding 2014 period. Significant new awards for the second quarter 2015 included a combined cycle gas turbine power project in the U.S. (approximately $600.0 million), an ethylene storage facility in the U.S. (approximately $115.0 million) and scope increases for our large nuclear projects in the U.S. ($350.0 million, including contractual entitlements, unapproved change orders and claims discussed further in Note 14 to our Financial Statements). Significant new awards for the second quarter 2014 included scope increases on our existing refinery project in Colombia and LNG mechanical erection project in the Asia Pacific region (approximately $1.3 billion combined) and a combined cycle gas turbine power project in the U.S. (approximately $500.0 million). New awards for the first six months of 2015 were $2.5 billion compared with $6.6 billion for the corresponding 2014 period. The six month 2015 period included the aforementioned second quarter 2015 awards, and awards during the first quarter 2015, including our proportionate share of a $2.0 billion additional LNG train (approximately $675.0 million) for an LNG export facility in the U.S. that we are executing through a joint venture arrangement; scope increases for our mixed oxide fuel fabrication facility project in the U.S. and LNG mechanical erection project in the Asia Pacific region (approximately $360.0 million combined); and engineering and procurement services for a refinery project in Russia. The six month 2014 period included the aforementioned second quarter 2014 awards, and awards during the first quarter 2014, including our proportionate share of a $6.2 billion LNG export facility in the U.S. (approximately $3.1 billion) that we are executing through a joint venture arrangement; structural, mechanical and piping construction work for an LNG project in the Asia Pacific Region (approximately $625.0 million); engineering and procurement for a clean fuels project in the Middle East (approximately $370.0 million); engineering and project management services for a pipeline expansion project in the Middle East (approximately $85.0 million); and front-end engineering for a plastics project in the Middle East (approximately $40.0 million).

30

Table of Contents

        
Revenue—Revenue was $1.9 billion for the second quarter 2015, representing a decrease of $23.8 million (1%) compared with the corresponding 2014 period. Revenue for the first six months of 2015 was $3.7 billion, representing an increase of $108.6 million (3%), compared with the corresponding 2014 period. Our second quarter and year-to-date 2015 results benefited from increased revenue on our large U.S. nuclear projects (approximately $125.0 million and $265.0 million, respectively) and LNG projects in the U.S. (approximately $250.0 million and $400.0 million, respectively). This benefit was offset for the second quarter 2015, and partly offset for the year-to-date 2015 period, by a net decrease in revenue on our cost reimbursable LNG mechanical erection and gas processing projects in the Asia Pacific region and refinery project in Colombia (approximately $300.0 million and $350.0 million combined, respectively) and various other projects in the Asia Pacific region and Europe. Inclusive of the aforementioned project impacts, our second quarter and year-to-date 2015 revenue was unfavorably impacted relative to the 2014 periods by approximately $190.0 million and $320.0 million, respectively, due to foreign currency fluctuations associated with the strengthening of the U.S. Dollar against the Australian Dollar, British Pound, Canadian Dollar, Colombian Peso and Euro.
Approximately $530.0 million and $990.0 million of the operating group's quarter and year-to-date 2015 revenue, respectively, was attributable to our large U.S. nuclear projects, compared with approximately $405.0 million and $725.0 million, respectively, for the corresponding 2014 periods. Approximately $530.0 million and $1.2 billion of the operating group's second quarter and year-to-date 2015 revenue, respectively, were attributable to our large cost reimbursable projects, compared with approximately $830.0 million and $1.5 billion, respectively, for the corresponding 2014 periods.
Income from Operations—Income from operations for the second quarter 2015 was $176.5 million (9.2% of revenue), compared with $132.6 million (6.8% of revenue) for the corresponding 2014 period. Income from operations for the first six months of 2015 was $312.9 million (8.4% of revenue), compared with $217.3 million (6.0% of revenue) for the corresponding 2014 period. Our second quarter and year-to-date 2015 results were unfavorably impacted relative to the 2014 periods by approximately $14.0 million and $24.0 million, respectively, due to lower revenue volume resulting from foreign currency fluctuations associated with the strengthening of the U.S. Dollar, as noted in the Revenue section above. Our results for the second quarter and year-to-date 2015 period benefited from a higher margin backlog mix and benefited by approximately $28.0 million from the net impact of cost increases on our two U.S. nuclear projects, offset by the percent complete benefit of increases in project price on both projects related to contractual entitlements from our customers and consortium partner and an increase in claim recoveries on our South Carolina nuclear project, related to the aforementioned and previous forecast cost increases. Our second quarter and year-to-date 2014 results benefited from savings on two projects in Europe (approximately $14.0 million for both respective periods). See Note 14 to our Financial Statements for further discussion of our contractual entitlements, unapproved change orders and claims.
Fabrication Services
New Awards—New awards were $844.7 million for the second quarter 2015, compared with $564.4 million for the corresponding 2014 period. Significant new awards for the second quarter 2015 included scope increases for our large nuclear projects in the U.S. (approximately $250.0 million, including contractual entitlements, unapproved change orders and claims discussed further in Note 14 to our Financial Statements), engineering and fabrication for a hydrotreater in the U.S. (approximately $95.0 million) and engineered products for a refinery in Russia (approximately $93.0 million). Significant new awards for the second quarter 2014 included storage spheres in the Middle East (approximately $60.0 million), engineered products for a refinery in the Middle East (approximately $50.0 million) and an ammonia storage tank in the U.S. (approximately $40.0 million). New awards for the first six months of 2015 were $1.8 billion, compared with $1.1 billion for the corresponding 2014 period. The six month 2015 period included the aforementioned second quarter 2015 awards, and awards during the first quarter 2015, including work scopes we will perform for our U.S. LNG export facility projects that we are executing through our joint venture arrangements; storage tanks for a clean fuels project in the Middle East (approximately $60.0 million); an oil sands project in Canada (approximately $50.0 million); and pipe fabrication for a petrochemical project in the U.S. (approximately $40.0 million). The six month 2014 period included the aforementioned second quarter 2014 awards, and awards during the first quarter 2014, including pipe fabrication for a propane dehydrogenation unit in the U.S. (approximately $100.0 million).
Revenue—Revenue was $611.3 million for the second quarter 2015, representing a decrease of $83.0 million (12%) compared with the corresponding 2014 period. Revenue for the first six months of 2015 was $1.2 billion, representing a decrease of $117.1 million (9%), compared with the corresponding 2014 period. Our second quarter and year-to-date 2015 results were primarily impacted by lower storage tank work in the Asia Pacific region (approximately $120.0 million and $215.0 million, respectively), partly offset by increased engineered products activity (approximately $45.0 million and $95.0 million, respectively) and storage tank work in North America (approximately $35.0 million and $75.0 million, respectively). Inclusive of the aforementioned project impacts, our second quarter and year-to-date 2015 revenue was unfavorably impacted relative to the 2014 periods by approximately $40.0 million and $60.0 million, respectively, due to foreign currency fluctuations associated with the strengthening of the U.S. Dollar against the Australian Dollar and Canadian Dollar.

31

Table of Contents

Income from Operations—Income from operations for the second quarter 2015 was $55.9 million (9.2% of revenue), compared with $78.3 million (11.3% of revenue) for the corresponding 2014 period. Income from operations for the first six months of 2015 was $108.3 million (8.7% of revenue), compared with $125.2 million (9.2% of revenue) for the corresponding 2014 period. Our second quarter 2015 results were primarily impacted by lower revenue volume, a lower margin mix on our pipe fabrication backlog and cost increases on a project in the U.S. (approximately $12.0 million). Our year-to-date 2015 results were impacted by the aforementioned second quarter impacts, as well as lower revenue volume and a foreign exchange loss (approximately $11.0 million) associated with the re-measurement of certain non-U.S. Dollar denominated net assets during the first quarter 2015. Our second quarter 2014 results benefited from savings on various low temperature and cryogenic storage tank projects in the U.S. and Asia Pacific region (approximately $15.0 million), partly offset by the temporary underutilization of our pipe fabrication capacity due to customer delays (approximately $11.0 million). Our year-to-date 2014 results were impacted by the aforementioned second quarter 2014 impacts and a temporary underutilization of our pipe fabrication capacity in the first quarter 2014 due to customer delays (approximately $17.0 million).
Technology
New Awards—New awards were $81.1 million for the second quarter 2015, compared with $152.4 million for the corresponding 2014 period. New awards for the first six months of 2015 were $158.1 million, compared with $229.8 million for the corresponding 2014 period. The second quarter and year-to-date 2015 periods included various awards for refining and petrochemical licensing throughout the world. Awards for the second quarter and year-to-date 2014 periods included gas processing facilities in Africa and the U.S., CATOFIN propane dehydrogenation and olefins licensing in China, grass roots ethylene licensing in the Middle East, and refining licensing in India.
Revenue—Revenue was $93.0 million for the second quarter 2015, representing a decrease of $9.4 million (9%) compared with the corresponding 2014 period. Revenue for the first six months of 2015 was $192.3 million, representing a decrease of $12.6 million (6%) compared with the corresponding 2014 period. Our second quarter and year-to-date 2015 results were primarily impacted by the timing of awards and lower catalyst volume.
Income from Operations—Income from operations for the second quarter 2015 was $36.7 million (39.5% of revenue), compared with $37.2 million (36.4% of revenue) for the corresponding 2014 period. Income from operations for the first six months of 2015 was $84.8 million (44.1% of revenue), compared with $71.9 million (35.1% of revenue) for the corresponding 2014 period. The decrease in absolute dollars for the second quarter 2015 was due to lower revenue volume, and the increase as a percentage of revenue was primarily due to a higher margin mix of work. The increases in absolute dollars and as a percentage of revenue for the year-to-date 2015 period were primarily attributable to a higher margin mix of work and the aforementioned gain (approximately $7.5 million) associated with the contribution of a technology to our unconsolidated CLG joint venture during the first quarter 2015.
Capital Services
New Awards—New awards were $612.8 million for the second quarter 2015, compared with $1.4 billion for the corresponding 2014 period. Significant new awards for the second quarter 2015 included nuclear power plant services in the U.S. (approximately $250.0 million), refinery maintenance services in South America (approximately $120.0 million) and coking unit services in Canada (approximately $50.0 million). Significant new awards for the second quarter 2014 included nuclear power plant services in the U.S. (approximately $800.0 million), a chemical plant services project in the U.S. (approximately $110.0 million), an earthworks and soil stabilization project in the U.S. (approximately $100.0 million) and a support services project for the U.S. Environmental Protection Agency. New awards for the first six months of 2015 were $1.4 billion, compared with $2.1 billion for the corresponding 2014 period. The six month 2015 period included the aforementioned second quarter 2015 awards, and awards during the first quarter 2015, including refinery maintenance work in the U.S. and Canada (approximately $310.0 million combined) and scope increases on a chemical plant expansion project in the U.S. (approximately $115.0 million). The six month 2014 period included the aforementioned second quarter 2014 awards, and awards during the first quarter 2014, including nuclear facility modification work in the U.S. (approximately $120.0 million), environmental monitoring services in the U.S. (approximately $60.0 million) and environmental remediation services in the U.S. (approximately $35.0 million).
Revenue—Revenue was $586.7 million for the second quarter 2015, representing an increase of $28.9 million (5%) compared with the corresponding 2014 period. Revenue for the first six months of 2015 was $1.2 billion, representing an increase of $131.4 million (13%), compared with the corresponding 2014 period. Our second quarter and year-to-date 2015 results primarily benefited from increased plant maintenance revenue in the U.S. (approximately $15.0 million and $110.0 million, respectively).
Income from Operations—Income from operations for the second quarter 2015 was $15.0 million (2.6% of revenue), compared with $21.6 million (3.9% of revenue) for the corresponding 2014 period. Income from operations for the first six months of 2015 was $24.9 million (2.2% of revenue), compared with $25.9 million (2.5% of revenue) for the corresponding 2014 period. The decrease in absolute dollars and as a percentage of revenue for the second quarter 2015 was primarily due to

32

Table of Contents

reserves established during the second quarter 2015 for two uncollectible receivables (approximately $7.0 million). Our year-to-date 2015 results were impacted by the aforementioned second quarter receivable reserves, offset partly by higher revenue volume and continuing benefits from previously implemented cost reduction initiatives.
LIQUIDITY AND CAPITAL RESOURCES
General
Cash and Cash Equivalents—At June 30, 2015, our cash and cash equivalents were $355.1 million, and were maintained in local accounts throughout the world, substantially all of which were maintained outside The Netherlands, our country of domicile. With the exception of $192.2 million of cash and cash equivalents within our variable interest entities (“VIEs”) associated with our partnering arrangements, which is generally only available for use in our operating activities when distributed to the partners, we are not aware of any material restrictions on our cash and cash equivalents.
With respect to tax consequences associated with repatriating our foreign earnings, distributions from our European Union ("EU") subsidiaries to their Netherlands parent companies are not subject to taxation. Further, for our non-EU companies and their subsidiaries and our U.S. companies, to the extent taxes apply, the amount of permanently reinvested earnings becomes taxable upon repatriation of assets from the subsidiary or liquidation of the subsidiary. We have accrued taxes on undistributed earnings that we intend to repatriate, and we intend to permanently reinvest the remaining undistributed earnings in their respective businesses, and accordingly, have accrued no taxes on such amounts.
Summary of Cash Flow Activity
Operating Activities—During the first six months of 2015, net cash used in operating activities was $194.7 million, primarily resulting from cash generated from earnings, offset by a net change of $730.6 million in our accounts receivable, inventory, accounts payable and net contracts in progress account balances (collectively “Contract Capital”). During the second quarter 2015, net cash provided by operating activities was $95.2 million, primarily resulting from cash generated from earnings, partly offset by a net change in Contract Capital of $131.8 million. The components of our net Contract Capital balances at June 30, 2015 and December 31, 2014, and changes during the six months ended June 30, 2015, were as follows:
(In thousands)
June 30,
2015
 
December 31,
2014
 
Change
Billings in excess of costs and estimated earnings (1)
$
(1,687,409
)
 
$
(1,426,728
)
 
$
(260,681
)
Margin fair value liability for acquired contracts (2)
(502,175
)
 
(558,760
)
 
56,585

Total billings in excess of costs and estimated earnings
$
(2,189,584
)

$
(1,985,488
)

$
(204,096
)
Total costs and estimated earnings in excess of billings (1)
1,605,190

 
774,644

 
830,546

Contracts in progress, net
$
(584,394
)

$
(1,210,844
)

$
626,450

Accounts receivable, net
1,326,858

 
1,306,567

 
20,291

Inventory
292,244

 
286,155

 
6,089

Accounts payable
(1,179,056
)
 
(1,256,854
)
 
77,798

Contract Capital, net
$
(144,348
)

$
(874,976
)

$
730,628

(1) 
Represents our cash position relative to revenue recognized on projects, with (i) billings in excess of costs and estimated earnings representing a liability reflective of future cash expenditures and non-cash earnings, and (ii) costs and estimated earnings in excess of billings representing an asset reflective of future cash receipts.
(2) 
Represents a margin fair value liability associated with long-term contracts acquired in connection with the acquisition of The Shaw Group Inc. on February 13, 2013 (the "Acquisition Closing Date"). The margin fair value liability was approximately $745.5 million at the Acquisition Closing Date and is recognized as revenue on a percentage of completion basis as the applicable projects progress. We anticipate the remaining liability will be recognized as revenue over the next five years.
Fluctuations in our Contract Capital balance, and its components, are not unusual in our business and are impacted by the size of our projects and changing mix of cost-reimbursable versus fixed-price backlog. Our cost-reimbursable projects tend to have a greater working capital requirement ("cost and estimated earnings in excess of billings"), while our fixed-price projects are generally structured to be cash flow positive ("billings in excess of costs and estimated earnings"). Our Contract Capital is particularly impacted by the timing of new awards and related payments in advance of performing work, and the achievement of billing milestones on backlog as we complete certain phases of work. Contract Capital is also impacted at period-end by the timing of accounts receivable collections and accounts payable payments for our large projects.

33

Table of Contents

The $730.6 million decline in our Contract Capital liability during the first six months of 2015 was primarily due to a $56.6 million decrease in the margin fair value liability discussed above, a $660.4 million increase in the net Contract Capital asset position on our two large U.S. nuclear projects (exclusive of the margin fair value liability), and a $13.6 million decline in our net Contract Capital liability position on our remaining backlog. The Contract Capital position on our U.S. nuclear projects continues to be impacted by the timing of achievement of billing milestones and will continue to fluctuate prospectively based on the timing of achievement of future billing milestones and the timing of resolution of the recorded unapproved change orders and claims for the projects (see Note 14 to our Financial Statements). The Contract Capital position on the U.S. nuclear projects was also impacted by a decline in accounts payable of $34.7 million. The decline in our Contract Capital liability for the remainder of our backlog was primarily due to the timing of accounts payable payments, which resulted in a decline in accounts payable of $43.1 million, which was partly offset by receivable collections and payments in advance of performing work on our projects.
Although we anticipate future quarterly variability in our operating cash flows due to ongoing fluctuations in our Contract Capital balance (including the two U.S. nuclear projects), we expect cash flows from operating activities to approximate earnings for 2015. Further, we believe our anticipated future operating cash flows and capacity under our revolving and other credit facilities will be sufficient to finance our capital expenditures, settle our commitments and contingencies and address our working capital needs for the foreseeable future.
As discussed further below, in July 2015, we entered into financing agreements which amend or extend our existing credit facilities and establish additional financing capacity. These changes are the result of our assessment of the lending environment, and contemplate ongoing growth in our end markets and our strategic initiatives.
Investing Activities—During the first six months of 2015, net cash used in investing activities was $189.6 million, primarily related to net advances of $122.4 million to our venture partners by our proportionately consolidated ventures (see Note 6 to our Financial Statements for further discussion) and capital expenditures of $63.7 million. We will continue to evaluate and selectively pursue other opportunities for additional expansion of our business through the acquisition of complementary businesses and technologies. These acquisitions may involve the use of cash or may require further debt or equity financing.
Financing Activities—During the first six months of 2015, net cash provided by financing activities was $422.2 million, primarily related to net revolving facility and other short-term borrowings of $432.0 million, net advances from our proportionately consolidated ventures of $84.9 million (see Note 6 to our Financial Statements for further discussion) and cash proceeds from the issuance of shares associated with our stock plans of $11.1 million. These cash inflows were partly offset by repayments on our long-term debt of $53.0 million, distributions to our noncontrolling interest partners of $24.0 million, dividends paid to our shareholders of $15.2 million and share repurchases totaling $13.9 million (0.3 million shares at an average price of $40.96 per share), including $12.5 million to repurchase shares associated with stock-based compensation-related withholding taxes on taxable share distributions and $1.4 million to purchase shares of our outstanding common stock.
Effect of Exchange Rate Changes on Cash and Cash Equivalents—During the first six months of 2015, our cash and cash equivalents balance decreased by $34.1 million due to the impact of changes in functional currency exchange rates against the U.S. Dollar for non-U.S. Dollar cash balances, primarily the change in the Australian Dollar and Euro exchange rates. The net unrealized loss on our cash and cash equivalents resulting from these exchange rate movements is reflected in the cumulative translation adjustment component of OCI. Our cash and cash equivalents held in non-U.S. Dollar currencies are used primarily for project-related and other operating expenditures in those currencies, and therefore, our exposure to realized exchange gains and losses is not anticipated to be material.
Credit Facilities and Debt
General—Our primary internal source of liquidity is cash flow generated from operations. Capacity under our revolving credit and other facilities discussed below is also available, if necessary, to fund operating or investing activities and provide necessary letters of credit. Letters of credit are generally issued to customers in the ordinary course of business to support advance payments and performance guarantees, in lieu of retention on our contracts, or in certain cases, are issued in support of our insurance programs.
Committed Facilities—We have a five-year, $1.35 billion, committed and unsecured revolving facility (the “Revolving Facility”) with Bank of America ("BofA"), as administrative agent, and BNP Paribas Securities Corp., BBVA Compass, Credit Agricole Corporate and Investment Bank (“Credit Agricole”) and The Royal Bank of Scotland plc, each as syndication agents, which expires in October 2018. The Revolving Facility has a $675.0 million aggregate borrowing and financial letter of credit sublimit (with financial letters of credit not to exceed $270.0 million) and certain financial covenants, including a maximum leverage ratio of 3.00, a minimum fixed charge coverage ratio of 1.75, and a minimum net worth level calculated as $2.1 billion at June 30, 2015. The Revolving Facility also includes customary restrictions regarding subsidiary indebtedness, sales of assets, liens, investments, type of business conducted, and mergers and acquisitions, and includes a trailing twelve-month limitation of $250.0 million for dividend payments and share repurchases if our leverage ratio exceeds 1.50 (unlimited if our leverage ratio

34

Table of Contents

is equal to or below 1.50), among other restrictions. In addition to interest on debt borrowings, we are assessed quarterly commitment fees on the unutilized portion of the facility as well as letter of credit fees on outstanding instruments. The interest, commitment fee, and letter of credit fee percentages are based upon our quarterly leverage ratio. In the event we borrow funds under the facility, interest is assessed at either prime plus an applicable floating margin (3.25% and 0.50%, respectively at June 30, 2015), or LIBOR plus an applicable floating margin (0.19% and 1.50%, respectively at June 30, 2015). At June 30, 2015, we had $300.0 million of outstanding borrowings under the facility and $201.1 million of outstanding letters of credit under the facility (none of which were financial letters of credit), providing $848.9 million of available capacity, of which $375.0 million may be utilized for borrowings. During the first six months of 2015, our weighted average interest rate on borrowings under the facility was approximately 1.8%, inclusive of the applicable floating margin.
Effective July 8, 2015, we amended the Revolving Facility to remove the borrowing sublimit. The amended facility maintains the $270.0 million sublimit for financial letters of credit, and has financial and restrictive covenants similar to those of the previous facility.
We also have a five-year, $650.0 million, committed and unsecured revolving credit facility (the “Second Revolving Facility”) with BofA, as administrative agent, and Credit Agricole, as syndication agent, which expires in February 2018. The Second Revolving Facility, which supplements our Revolving Facility, has a $487.5 million borrowing and financial letter of credit sublimit and includes financial and restrictive covenants similar to those noted above for the Revolving Facility. In addition to interest on debt borrowings, we are assessed quarterly commitment fees on the unutilized portion of the facility as well as letter of credit fees on outstanding instruments. The interest, commitment fee, and letter of credit fee percentages are based upon our quarterly leverage ratio. In the event we borrow funds under the facility, interest is assessed at either prime plus an applicable floating margin (3.25% and 0.50% at June 30, 2015), or LIBOR plus an applicable floating margin (0.19% and 1.50% at June 30, 2015). At June 30, 2015, we had $59.0 million of outstanding borrowings and $19.5 million of outstanding letters of credit under the facility (including $4.0 million of financial letters of credit), providing $571.5 million of available capacity, of which $424.5 million may be utilized for borrowings. During the first six months of 2015, our weighted average interest rate on borrowings under the facility was approximately 3.8%, inclusive of the applicable floating margin.
Effective July 8, 2015, we amended and restated the Second Revolving Facility to increase the overall capacity to $800.0 million, extend the expiration date to July 8, 2020, remove the borrowing sublimit, and provide a financial letter of credit sublimit of $50.0 million. The amended facility has financial and restrictive covenants similar to those of the previous facility.
    
Uncommitted Facilities—We also have various short-term, uncommitted letter of credit and borrowing facilities (the "Uncommitted Facilities") across several geographic regions of approximately $3.6 billion, of which $440.0 million may be utilized for borrowings ($439.3 million at June 30, 2015, net of letter of credit utilization of $0.7 million under certain facilities). At June 30, 2015, we had $237.7 million of outstanding borrowings and $1.2 billion of outstanding letters of credit under these facilities, providing $2.1 billion of available capacity, of which $201.6 million may be utilized for borrowings. During the first six months of 2015, our weighted average interest rate on borrowings under the facility was approximately 1.2%.
Term Loan—At June 30, 2015, we had $775.0 million outstanding on our four-year, $1.0 billion unsecured term loan (the "Term Loan") with BofA as administrative agent. Interest and principal under the Term Loan is payable quarterly in arrears and bears interest at LIBOR plus an applicable floating margin (0.19% and 1.50%, respectively at June 30, 2015). However, we continue to utilize an interest rate swap to hedge against $391.4 million of the outstanding $775.0 million Term Loan, which resulted in a weighted average interest rate of approximately 2.0% during the first six months of 2015, inclusive of the applicable floating margin. Future annual maturities for the Term Loan are $50.0 million, $150.0 million and $575.0 million for the remainder of 2015, 2016 and 2017, respectively. The Term Loan includes financial and restrictive covenants similar to those noted above for the Revolving Facility.
Effective July 8, 2015, we entered into a $500.0 million term loan (the “Second Term Loan”). The Second Term Loan requires that $275.0 million of the loan proceeds be utilized to prepay a portion of the 2017 principal due on the Term Loan. Thereafter, interest and principal under the Second Term Loan is payable quarterly in arrears beginning in June 2017 and bears interest at LIBOR plus an applicable floating margin (rates are equivalent to the Term Loan). Future annual maturities for the Second Term Loan are $56.3 million, $75.0 million, $75.0 million and $293.8 million for 2017, 2018, 2019, and 2020, respectively. The Second Term Loan has financial and restrictive covenants similar to those of the Term Loan.
Senior Notes—We have a series of senior notes totaling $800.0 million in the aggregate (the "Senior Notes"), with Merrill Lynch, Pierce, Fenner & Smith Incorporated, and Credit Agricole, as administrative agents. The Senior Notes have financial and restrictive covenants similar to those noted above for the Revolving Facility. The Senior Notes include Series A through D, which contain the following terms:
Series A—Interest due semi-annually at a fixed rate of 4.15%, with principal of $150.0 million due in December 2017
Series B—Interest due semi-annually at a fixed rate of 4.57%, with principal of $225.0 million due in December 2019

35

Table of Contents

Series C—Interest due semi-annually at a fixed rate of 5.15%, with principal of $275.0 million due in December 2022
Series D—Interest due semi-annually at a fixed rate of 5.30%, with principal of $150.0 million due in December 2024
Effective July 22, 2015, we entered into a $200.0 million note purchase and guarantee agreement (the "New Senior Note"). Interest is due semi-annually at a fixed rate of 4.53%, with principal of $200.0 million due in July 2025. The New Senior Note has financial and restrictive covenants similar to those of the Senior Notes.
Other Long-Term Debt—At June 30, 2015, we also had $42.2 million outstanding on a $48.1 million six-year secured (construction equipment) term loan. Interest and principal under the loan is payable monthly in arrears and bears interest at 3.26%. Future annual maturities are $3.0 million, $6.2 million, $6.4 million, $6.6 million, $6.8 million and $13.1 million for the remainder of 2015, 2016, 2017, 2018, 2019 and 2020, respectively.
Compliance and Other—During the first six months of 2015, maximum outstanding borrowings under our revolving credit and other facilities was approximately $1.1 billion. In addition to providing letters of credit, we also issue surety bonds in the ordinary course of business to support our contract performance. At June 30, 2015, we had $689.2 million of outstanding surety bonds.
At June 30, 2015, we were in compliance with all of our restrictive and financial covenants associated with our debt and revolving credit and other facilities, with a leverage ratio of 1.83, a fixed charge coverage ratio of 5.82, and net worth of $3.0 billion. Our ability to remain in compliance with our lending facilities could be impacted by circumstances or conditions beyond our control, including, but not limited to, the delay or cancellation of projects, changes in foreign currency exchange or interest rates, performance of pension plan assets, or changes in actuarial assumptions. Further, we could be impacted if our customers experience a material change in their ability to pay us or if the banks associated with our lending facilities were to cease or reduce operations, or if there is a full or partial break-up of the EU or its currency, the Euro.
Other
We believe our cash on hand, cash generated from operations, amounts available under our Revolving Facility and Second Revolving Facility (collectively, "Committed Facilities") and Uncommitted Facilities, and other external sources of liquidity, such as the issuance of debt and equity instruments, will be sufficient to finance our capital expenditures, settle our commitments and contingencies (as more fully described in Note 11 to our Financial Statements) and address our working capital needs for the foreseeable future. However, there can be no assurance that such funding will continue to be available, as our ability to generate cash flows from operations and our ability to access funding under our Committed Facilities and Uncommitted Facilities at reasonable terms, may be impacted by a variety of business, economic, legislative, financial and other factors, which may be outside of our control.
Additionally, while we currently have significant uncommitted bonding facilities, primarily to support various commercial provisions in our contracts, a termination or reduction of these bonding facilities could result in the utilization of letters of credit in lieu of performance bonds, thereby reducing the available capacity under the Committed Facilities. Although we do not anticipate a reduction or termination of the bonding facilities, there can be no assurance that such facilities will continue to be available at reasonable terms to service our ordinary course obligations.
A portion of our pension plans' assets are invested in EU government securities, which could be impacted by economic turmoil in Europe or a full or partial break-up of the EU or its currency, the Euro. However, given the long-term nature of pension funding requirements, in the event any of our pension plans (including those with investments in EU government securities) become materially underfunded from a decline in value of our plan assets, we believe our cash on hand and amounts available under our existing Committed Facilities and Uncommitted Facilities would be sufficient to fund any increases in future contribution requirements.
We are a defendant in a number of lawsuits arising in the normal course of business and we have in place appropriate insurance coverage for the type of work that we perform. As a matter of standard policy, we review our litigation accrual quarterly and as further information is known on pending cases, increases or decreases, as appropriate, may be recorded. See Note 11 to our Financial Statements for a discussion of pending litigation, including lawsuits wherein plaintiffs allege exposure to asbestos due to work we may have performed.
OFF-BALANCE SHEET ARRANGEMENTS
We use operating leases for facilities and equipment when they make economic sense, including sale-leaseback arrangements. Our sale-leaseback arrangements are not material to our Financial Statements, and we have no other significant off-balance sheet arrangements.
NEW ACCOUNTING STANDARDS
See the applicable section of Note 2 to our Financial Statements for a discussion of new accounting standards.

36

Table of Contents

CRITICAL ACCOUNTING ESTIMATES
The discussion and analysis of our financial condition and results of operations are based upon our Financial Statements, which have been prepared in accordance with U.S. GAAP. The preparation of these Financial Statements requires us to make estimates and judgments that affect the reported amounts of assets, liabilities, revenue and expenses and related disclosures of contingent assets and liabilities. We continually evaluate our estimates based upon historical experience and various other assumptions that we believe to be reasonable under the circumstances. Our management has discussed the development and selection of our critical accounting estimates with the Audit Committee of our Supervisory Board of Directors. Actual results may differ from these estimates under different assumptions or conditions. We believe the following critical accounting policies affect our more significant judgments and estimates used in the preparation of our Financial Statements.
Revenue Recognition—Our revenue is primarily derived from long-term contracts and is generally recognized using the POC method, primarily based on the percentage that actual costs-to-date bear to total estimated costs to complete each contract. We follow the guidance of FASB ASC Revenue Recognition Topic 605-35 for accounting policies relating to our use of the POC method, estimating costs, and revenue recognition, including the recognition of incentive fees, unapproved change orders and claims, and combining and segmenting contracts. We primarily utilize the cost-to-cost approach to estimate POC as we believe this method is less subjective than relying on assessments of physical progress. Under the cost-to-cost approach, the use of estimated costs to complete each contract is a significant variable in the process of determining recognized revenue and is a significant factor in the accounting for contracts. Significant estimates that impact the cost to complete each contract are costs of engineering, materials, components, equipment, labor and subcontracts; labor productivity; schedule durations, including subcontractor or supplier progress; liquidated damages; contract disputes, including claims; achievement of contractual performance requirements; and contingency, among others. The cumulative impact of revisions in total cost estimates during the progress of work is reflected in the period in which these changes become known, including, to the extent required, the reversal of profit recognized in prior periods and the recognition of losses expected to be incurred on contracts in progress. Due to the various estimates inherent in our contract accounting, actual results could differ from those estimates.
Our long-term contracts are awarded on a competitively bid and negotiated basis and the timing of revenue recognition may be impacted by the terms of such contracts. We use a range of contracting options, including cost-reimbursable, fixed-price and hybrid, which has both cost-reimbursable and fixed-price characteristics. Fixed-price contracts, and hybrid contracts with a more significant fixed-price component, tend to provide us with greater control over project schedule and the timing of when work is performed and costs are incurred, and accordingly, when revenue is recognized. Cost-reimbursable contracts, and hybrid contracts with a more significant cost-reimbursable component, generally provide our customers with greater influence over the timing of when we perform our work, and accordingly, such contracts often result in less predictability with respect to the timing of revenue recognition. Contract revenue for our long-term contracts recognized under the POC method reflects the original contract price adjusted for approved change orders and estimated recoveries for incentive fees, unapproved change orders and claims. We recognize revenue associated with incentive fees when the value can be reliably estimated and recovery is probable. We recognize revenue associated with unapproved change orders and claims to the extent the related costs have been incurred, the value can be reliably estimated and recovery is probable. Our recorded incentive fees, unapproved change orders and claims reflect our best estimate of recovery amounts; however, the ultimate resolution and amounts received could differ from these estimates. See Note 14 to our Financial Statements for additional discussion of our recorded unapproved change orders, claims, incentives and other contract recoveries.
With respect to our EPC services, our contracts are not segmented between types of services, such as engineering and construction, if each of the EPC components is negotiated concurrently or if the pricing of any such services is subject to the ultimate negotiation and agreement of the entire EPC contract. However, an EPC contract including technology or fabrication services may be segmented if we satisfy the segmenting criteria in ASC 605-35. Revenue recorded in these situations is based on our prices and terms for similar services to third party customers. Segmenting a contract may result in different interim rates of profitability for each scope of service than if we had recognized revenue without segmenting. In some instances, we may combine contracts that are entered into in multiple phases, but are interdependent and include pricing considerations by us and the customer that are impacted by all phases of the project. Otherwise, if each phase is independent of the other and pricing considerations do not give effect to another phase, the contracts will not be combined.
Cost of revenue for our long-term contracts includes direct contract costs, such as materials and labor, and indirect costs that are attributable to contract activity. The timing of when we bill our customers is generally dependent upon advance billing terms, milestone billings based on the completion of certain phases of the work, or when services are provided. Projects with cumulative costs and estimated earnings recognized to date in excess of cumulative billings is reported on the Balance Sheet as costs and estimated earnings in excess of billings. Projects with cumulative billings in excess of costs and estimated earnings recognized to date is reported on the Balance Sheet as billings in excess of costs and estimated earnings. Any uncollected billed revenue, including contract retentions, is reported as accounts receivable.

37

Table of Contents

Revenue for our service contracts that do not satisfy the criteria for revenue recognition under the POC method is recorded at the time services are performed. Revenue associated with incentive fees for these contracts is recognized when earned. Unbilled receivables for our service contracts are recorded within accounts receivable.
Revenue for our pipe and steel fabrication and catalyst manufacturing contracts that are independent of an EPC contract, or for which we satisfy the segmentation criteria discussed above, is recognized upon shipment of the fabricated or manufactured units. During the fabrication or manufacturing process, all related direct and allocable indirect costs are capitalized as work in process inventory and such costs are recorded as cost of revenue at the time of shipment.
Recoverability of Goodwill—At June 30, 2015, our goodwill balance was $4.2 billion. Goodwill is not amortized to earnings, but instead is reviewed for impairment at least annually at a reporting unit level, absent any indicators of impairment. We perform our annual impairment assessment during the fourth quarter of each year based upon balances as of October 1. At December 31, 2014, we had the following seven reporting units within our four operating groups:
Engineering, Construction & Maintenance—Our Engineering, Construction & Maintenance operating group included three reporting units: Oil & Gas, Power and Plant Services.
Fabrication Services—Our Fabrication Services operating group included two reporting units: Steel Plate Structures and Fabrication & Manufacturing.
Technology—Our Technology operating group represented a reporting unit.
Environmental Solutions—Our Environmental Solutions operating group represented a reporting unit.
As part of our annual impairment assessment, in the fourth quarter 2014, we performed a quantitative assessment of goodwill for each of the aforementioned reporting units. Based upon this quantitative assessment, the fair value of each of our seven reporting units exceeded their respective net book values, and accordingly, no impairment charge was necessary during 2014.
During the first quarter 2015, we realigned our four operating groups, which represent our reportable segments, as discussed further in Note 15 to our Financial Statements, and in connection therewith, we realigned our reporting units. Accordingly, at June 30, 2015, we had the following eight reporting units within our four realigned operating groups:
Engineering & Construction (formerly Engineering, Construction & Maintenance)—Our Engineering & Construction operating group includes two reporting units: Oil & Gas and Power. Our Plant Services reporting unit was reclassified to our realigned Capital Services operating group, as noted below.
Fabrication Services—Our Fabrication Services operating group includes three reporting units: Steel Plate Structures, Fabrication & Manufacturing, and Engineered Products. Our Engineered Products reporting unit represents a portion of our previous Technology reporting unit.
Technology—Our Technology operating group continues to represent a reporting unit, consisting of the remaining portion of our previous Technology reporting unit, after reclassification of the Engineered Products reporting unit to Fabrication Services, as noted above.
Capital Services (formerly Environmental Solutions)—Our Capital Services operating group includes two reporting units: Facilities & Plant Services and Federal Services. Our Facilities & Plant Services reporting unit represents our previous Plant Services reporting unit and a portion of our previous Environmental Solutions reporting unit. Our Federal Services reporting unit represents the remaining portion of our previous Environmental Solutions reporting unit.
In conjunction with the aforementioned realignment of our operating groups, we allocated goodwill among our new and realigned reporting units based on the relative fair value of the reporting units being realigned. As a result, during the first quarter 2015, we performed a quantitative assessment of goodwill for each of the reporting units impacted by our operating group realignment, which included Engineered Products, Technology, Facilities & Plant Services, and Federal Services. Based on this quantitative assessment, the fair value of each of the reporting units impacted by our operating group realignment exceeded their respective net book values, and accordingly, no impairment charge was necessary as a result of the realignment. The fair value of the new Engineered Products and realigned Technology reporting units substantially exceeded their respective net book values. The fair value of the realigned Federal Services and Facilities & Plant Services reporting units (both acquired in 2013 and discussed further below) exceeded their respective net book values by approximately 38% and 14%, respectively. Additionally, during the first of six months of 2015, no indicators of goodwill impairment were identified for any of our reporting units. If, based on future assessments our goodwill is deemed to be impaired, the impairment would result in a charge to earnings in the period of impairment.

38

Table of Contents

To determine the fair value of our reporting units and test for impairment, we utilized an income approach (discounted cash flow method) as we believe this is the most direct approach to incorporate the specific economic attributes and risk profiles of our reporting units into our valuation model. This is consistent with the methodology used to determine the fair value of our reporting units in previous years. We generally do not utilize a market approach given the lack of relevant information generated by market transactions involving comparable businesses. The discounted cash flow methodology is based, to a large extent, on assumptions about future events, which may or may not occur as anticipated, and such deviations could have a significant impact on the calculated estimated fair values of our reporting units. These assumptions include, but are not limited to, estimates of discount rates, future growth rates, and terminal values for each reporting unit. The discounted cash flow analysis for our reporting units included forecasted cash flows over a seven-year forecast period (2015 through 2021), with our 2015 business plan used as the basis for our 2015 projections. These forecasted cash flows took into consideration historical and recent results, the reporting unit’s backlog and near term prospects, and management’s outlook for the future. A terminal value was also calculated using a terminal value growth assumption to derive the annual cash flows after the discrete forecast period. A reporting unit specific discount rate was applied to the forecasted cash flows and terminal cash flows to determine the discounted future cash flows, or fair value, of each reporting unit. Further discussion regarding the fair values of the Federal Services and Facilities & Plant Services reporting units is below.
Federal Services—Goodwill associated with the Federal Services reporting unit was approximately $189.0 million at January 1, 2015, and the fair value of the reporting unit exceeded its net book value by approximately 38%. Key assumptions used in deriving the reporting unit’s fair value included a discount rate of 11.5%; an earnings before interest, taxes, depreciation and amortization (“EBITDA”) compound annual growth rate (“CAGR”) of approximately 9% from 2015 through 2021; and a terminal growth rate of 2.5%.
The Federal Services reporting unit provides mission critical base operations and maintenance, environmental engineering and remediation, infrastructure EPC services, and disaster response and recovery for federal governments. Ongoing uncertainty with respect to federal government funding and prioritization has impacted recent operating results for the reporting unit; however, cost reductions and other initiatives have enabled the reporting unit to partially mitigate these impacts. The reporting unit’s forecast and growth assumptions include 1) increases in environmental services and critical base infrastructure work, 2) increases in government funding or a greater share of the existing budgetary funding, and 3) continued benefits from its cost reduction initiatives. Accordingly, the fair value of the Federal Services reporting unit could be negatively impacted by lower than anticipated growth in environmental services and critical base infrastructure work, reductions in government spending or changes in prioritization, and increased competition within the government services sector. The fair value of the reporting unit could be positively impacted by a significant event (such as a natural disaster) that increases the demand for the reporting unit’s emergency response and disaster recovery/program management services. While the reporting unit has benefited from such events historically, due to uncertainty with respect to timing, the reporting unit’s forecast and growth assumptions do not include such an event.
Facilities & Plant Services—Goodwill associated with the Facilities & Plant Services reporting unit was approximately $695.0 million at January 1, 2015, and the fair value of the reporting unit exceeded its net book value by approximately 14%. Key assumptions used in deriving the reporting unit’s fair value included a discount rate of 10%; an EBITDA CAGR of approximately 8% from 2015 through 2021; and a terminal growth rate of 2.5%.
The Facilities & Plant Services reporting unit provides maintenance and modifications services to nuclear and industrial facilities, environmental engineering and remediation, infrastructure EPC services, program management, and disaster response and recovery for private sector customers and state and local governments. The reporting unit is partially reliant upon securing and maintaining long-term nuclear and industrial maintenance contracts, which often include services for multiple facilities for a single customer. The contracts often cover three to five year periods and are subject to periodic renewal. The reporting unit’s forecast and growth assumptions include 1) maintaining these significant contracts (or replacing them with similar contracts), 2) expanding the reporting unit’s maintenance services outside the U.S. utilizing CB&I’s international footprint, 3) growth in construction, global coastal marine and environmental services, 4) continued participation in the new awards of other reporting units (“Pull-Through Services”), and 5) growth in craft services related to decommissioning activities associated with the retirement of North American power generation plants. Accordingly, the fair value of the Facilities & Plant Services reporting unit could be negatively impacted by the loss of a key customer relationship, lower than anticipated international expansion, lower than anticipated growth in global coastal marine, environmental, construction and decommissioning services, and reduced demand for Pull-Through Services due to delays in the award of large contracts for other reporting units. The fair value of the reporting unit could be positively impacted by a faster than expected international expansion (including a further diversification of associated services), new key customer relationships, and a larger than anticipated market share of construction and decommissioning activities.

39

Table of Contents

Recoverability of Other Long-Lived Assets—We amortize our finite-lived intangible assets on a straight-line basis with lives ranging from 3 to 20 years, absent any indicators of impairment. We review tangible assets and finite-lived intangible assets for impairment when events or changes in circumstances indicate that the carrying amount may not be recoverable. If a recoverability assessment is required, the estimated future cash flow associated with the asset or asset group will be compared to the asset’s carrying amount to determine if an impairment exists. We noted no indicators of impairment during the six months ended June 30, 2015. See Note 5 to our Financial Statements for further discussion regarding goodwill and other intangible assets.
Income Taxes—Deferred tax assets and liabilities are recognized for the future tax consequences attributable to differences between the financial statement carrying amounts of existing assets and liabilities and their respective tax basis using currently enacted income tax rates for the years in which the differences are expected to reverse. A valuation allowance is provided to offset any net deferred tax assets ("DTA(s)") if, based upon the available evidence, it is more likely than not that some or all of the DTAs will not be realized. The realization of our net DTAs depends upon our ability to generate sufficient future taxable income of the appropriate character and in the appropriate jurisdictions.
On a periodic and ongoing basis we evaluate our DTAs and assess the appropriateness of our valuation allowances ("VA"). In assessing the need for a VA, we consider both positive and negative evidence related to the likelihood of realization of the DTAs. If, based on the weight of available evidence, our assessment indicates that it is more likely than not that a DTA will not be realized, we record a VA. Our assessments include, among other things, the value and quality of our backlog, evaluations of existing and anticipated market conditions, analysis of recent and historical operating results and projections of future results, strategic plans and alternatives for associated operations, as well as asset expiration dates, where applicable. If the factors upon which we based our assessment of realizability of our DTAs differ materially from our expectations, including future operating results being lower than our current estimates, our future assessments could be impacted and result in an increase in VA and increase in tax expense.
Income tax and associated interest reserves, where applicable, are recorded in those instances where we consider it more likely than not that additional tax will be due in excess of amounts reflected in income tax returns filed worldwide, irrespective of whether or not we have received tax assessments. We continually review our exposure to additional income tax obligations and, as further information is known or events occur, changes in our tax and interest reserves may be recorded within income tax expense and interest expense, respectively.
Insurance—We maintain insurance coverage for various aspects of our business and operations. However, we retain a portion of anticipated losses through the use of deductibles and self-insured retentions for our exposures related to third party liability and workers’ compensation. We regularly review estimates of reported and unreported claims through analysis of historical and projected trends, in conjunction with actuaries and other consultants, and provide for losses through insurance reserves. As claims develop and additional information becomes available, adjustments to loss reserves may be required. If actual results are not consistent with our assumptions, we may be exposed to gains or losses that could be material.
Partnering ArrangementsIn the ordinary course of business, we execute specific projects and conduct certain operations through joint venture, consortium and other collaborative arrangements (collectively referred to as “venture(s)”). We have various ownership interests in these ventures, with such ownership typically being proportionate to our decision making and distribution rights. The ventures generally contract directly with the third party customer; however, services may be performed directly by the ventures, or may be performed by us, our partners, or a combination thereof.
Venture net assets consist primarily of working capital and property and equipment, and assets may be restricted from being used to fund obligations outside of the venture. These ventures typically have limited third party debt or have debt that is non-recourse in nature; however, they may provide for capital calls to fund operations or require participants in the venture to provide additional financial support, including advance payment or retention letters of credit.
Each venture is assessed at inception and on an ongoing basis as to whether it qualifies as a VIE under the consolidations guidance in ASC 810. A venture generally qualifies as a VIE when it (1) meets the definition of a legal entity, (2) absorbs the operational risk of the projects being executed, creating a variable interest, and (3) lacks sufficient capital investment from the partners, potentially resulting in the venture requiring additional subordinated financial support, if necessary, to finance its future activities.
If at any time a venture qualifies as a VIE, we perform a qualitative assessment to determine whether we are the primary beneficiary of the VIE and, therefore, need to consolidate the VIE. We are the primary beneficiary if we have (1) the power to direct the economically significant activities of the VIE and (2) the right to receive benefits from, and obligation to absorb losses of, the VIE. If the venture is a VIE and we are the primary beneficiary, or we otherwise have the ability to control the venture, we consolidate the venture. If we are not determined to be the primary beneficiary of the VIE, or only have the ability to significantly influence, rather than control the venture, we do not consolidate the venture. We account for unconsolidated ventures using proportionate consolidation for both our Balance Sheet and Statement of Operations when we meet the

40

Table of Contents

applicable accounting criteria to do so and utilize the equity method otherwise. See Note 6 to our Financial Statements for additional discussion of our material partnering arrangements.
Financial Instruments—We utilize derivative instruments in certain circumstances to mitigate the effects of changes in foreign currency exchange rates and interest rates, as described below:
Foreign Currency Exchange Rate Derivatives—We do not engage in currency speculation; however, we utilize foreign currency exchange rate derivatives on an ongoing basis to hedge against certain foreign currency related operating exposures. We generally seek hedge accounting treatment for contracts used to hedge operating exposures and designate them as cash flow hedges. Therefore, gains and losses, exclusive of credit risk and forward points (which represent the time value component of the fair value of our derivative positions), are included in AOCI until the associated underlying operating exposure impacts our earnings. Changes in the fair value of (1) credit risk and forward points, (2) instruments deemed ineffective during the period, and (3) instruments that we do not designate as cash flow hedges, are recognized within cost of revenue.
Interest Rate Derivatives—At June 30, 2015, we continued to utilize a swap arrangement to hedge against interest rate variability associated with $391.4 million of our outstanding $775.0 million Term Loan. The swap arrangement has been designated as a cash flow hedge as its critical terms matched those of the Term Loan at inception and through June 30, 2015. Accordingly, changes in the fair value of the swap arrangement are included in AOCI until the associated underlying exposure impacts our earnings.
FORWARD-LOOKING STATEMENTS
This quarterly report on Form 10-Q, including all documents incorporated by reference, contains forward-looking statements regarding CB&I and represents our expectations and beliefs concerning future events. These forward-looking statements are intended to be covered by the safe harbor for forward-looking statements provided by the Private Securities Litigation Reform Act of 1995. Forward-looking statements involve known and unknown risks and uncertainties. When considering any statements that are predictive in nature, depend upon or refer to future events or conditions, or use or contain words, terms, phrases, or expressions such as “achieve,” “forecast,” “plan,” “propose,” “strategy,” “envision,” “hope,” “will,” “continue,” “potential,” “expect,” “believe,” “anticipate,” “project,” “estimate,” “predict,” “intend,” “should,” “could,” “may,” “might,” or similar forward-looking statements, we refer you to the cautionary statements concerning risk factors and “Forward-Looking Statements” described under “Risk Factors” in Item 1A of our 2014 Annual Report and any updates to those risk factors or “Forward-Looking Statements” included in our subsequent quarterly reports on Form 10-Q filed with the SEC, which cautionary statements are incorporated herein by reference.
Item 3. Quantitative and Qualitative Disclosures About Market Risk
Foreign Currency Risk—We are exposed to market risk associated with changes in foreign currency exchange rates, which may adversely affect our results of operations and financial condition. One form of exposure to fluctuating exchange rates relates to the effects of translating financial statements of foreign operations (primarily Australian Dollar, British Pound, Canadian Dollar, Colombian Peso and Euro denominated) into our reporting currency, which are recognized as a cumulative translation adjustment in AOCI. The change in the currency translation adjustment component of AOCI during the six months ended June 30, 2015 was a loss totaling $35.0 million, net of tax, primarily resulting from movements in the Australian Dollar and Euro exchange rates against the U.S. Dollar. We generally do not hedge our exposure to potential foreign currency translation adjustments.
We do not engage in currency speculation; however, we utilize foreign currency exchange rate derivatives on an ongoing basis to hedge against certain foreign currency related operating exposures. We generally seek hedge accounting treatment for contracts used to hedge operating exposures and designate them as cash flow hedges. Therefore, gains and losses, exclusive of credit risk and forward points, are included in AOCI until the associated underlying operating exposure impacts our earnings. Changes in the fair value of (1) credit risk and forward points, (2) instruments deemed ineffective during the period, and (3) instruments that we do not designate as cash flow hedges, are recognized within cost of revenue and were not material during the three and six months ended June 30, 2015.
At June 30, 2015, the notional value of our outstanding forward contracts to hedge certain foreign currency exchange-related operating exposures was $51.4 million, including net foreign currency exchange rate exposure associated with the purchase of Japanese Yen ($14.7 million), Euros ($13.3 million), Kuwaiti Dinars ($5.9 million), British Pounds ($1.2 million), Singapore Dollars ($0.6 million) and Chinese Renminbi ($0.5 million), and the sale of U.S. Dollars ($15.2 million). The total net fair value of these contracts was a loss of approximately $6.5 million at June 30, 2015. The potential change in fair value for our outstanding contracts resulting from a hypothetical ten percent change in quoted foreign currency exchange rates would have been approximately $4.9 million and $14.4 million at June 30, 2015 and December 31, 2014, respectively. This potential change in fair value of our outstanding contracts would be offset by the change in fair value of the associated underlying operating exposures.

41

Table of Contents

Interest Rate Risk—At June 30, 2015, we continued to utilize an interest rate swap to hedge against interest rate variability associated with $391.4 million of our outstanding $775.0 million Term Loan. The swap arrangement has been designated as a cash flow hedge as its critical terms matched those of the Term Loan at inception and through June 30, 2015. Accordingly, changes in the fair value of the interest rate swap are recognized in AOCI. The total net fair value of the contract was a loss of approximately $0.3 million at June 30, 2015. The potential change in fair value for our interest rate swap resulting from a hypothetical one percent change in the LIBOR rate would have been approximately $4.7 million and $6.9 million at June 30, 2015 and December 31, 2014, respectively.
Other—The carrying values of our accounts receivable and accounts payable approximate their fair values because of the short-term nature of these instruments. At June 30, 2015, the fair value of our Term Loan, based upon the current market rates for debt with similar credit risk and maturity, approximated its carrying value as interest is based upon LIBOR plus an applicable floating margin. Our Senior Notes are categorized within level 2 of the valuation hierarchy and had a total fair value of approximately $774.2 million and $785.1 million at June 30, 2015 and December 31, 2014, respectively, based on current market rates for debt with similar credit risk and maturities. See Note 9 to our Financial Statements for additional discussion of our financial instruments.
Item 4. Controls and Procedures
Disclosure Controls and Procedures—For the period covered by this quarterly report on Form 10-Q, we carried out an evaluation, under the supervision and with the participation of our management, including the Chief Executive Officer (“CEO”) and Chief Financial Officer (“CFO”), of the effectiveness of the design and operation of our disclosure controls and procedures (as such term is defined in Rules 13a-15(e) and 15d-15(e) under the Securities Exchange Act of 1934, as amended). Based upon such evaluation, the CEO and CFO have concluded that, as of the end of such period, our disclosure controls and procedures are effective.
Changes in Internal Control—There were no changes in our internal controls over financial reporting that occurred during the second quarter 2015, that have materially affected, or are reasonably likely to materially affect, our internal controls over financial reporting.
PART II. OTHER INFORMATION
Item 1. Legal Proceedings
General—We have been and may from time to time be named as a defendant in legal actions claiming damages in connection with engineering and construction projects, technology licenses, other services we provide, and other matters. These are typically claims that arise in the normal course of business, including employment-related claims and contractual disputes or claims for personal injury or property damage which occur in connection with services performed relating to project or construction sites. Contractual disputes normally involve claims relating to the timely completion of projects, performance of equipment or technologies, design or other engineering services or project construction services provided by us. We do not believe that any of our pending contractual, employment-related, personal injury or property damage claims and disputes will have a material adverse effect on our future results of operations, financial position or cash flow. See Note 14 to our Financial Statements for additional discussion of claims associated with our projects.
Asbestos Litigation—We are a defendant in lawsuits wherein plaintiffs allege exposure to asbestos due to work we may have performed at various locations. We have never been a manufacturer, distributor or supplier of asbestos products. Over the past several decades and through June 30, 2015, we have been named a defendant in lawsuits alleging exposure to asbestos involving approximately 5,800 plaintiffs and, of those claims, approximately 1,700 claims were pending and 4,100 have been closed through dismissals or settlements. Over the past several decades and through June 30, 2015, the claims alleging exposure to asbestos that have been resolved have been dismissed or settled for an average settlement amount of approximately two thousand dollars per claim. We review each case on its own merits and make accruals based upon the probability of loss and our estimates of the amount of liability and related expenses, if any. While we have seen an increase in the number of recent filings, especially in one specific venue, we do not believe that the increase or any unresolved asserted claims will have a material adverse effect on our future results of operations, financial position or cash flow, and at June 30, 2015, we had approximately $5.1 million accrued for liability and related expenses. With respect to unasserted asbestos claims, we cannot identify a population of potential claimants with sufficient certainty to determine the probability of a loss and to make a reasonable estimate of liability, if any. While we continue to pursue recovery for recognized and unrecognized contingent losses through insurance, indemnification arrangements or other sources, we are unable to quantify the amount, if any, that we may expect to recover because of the variability in coverage amounts, limitations and deductibles, or the viability of carriers, with respect to our insurance policies for the years in question.

42

Table of Contents

Environmental Matters—Our operations are subject to extensive and changing U.S. federal, state and local laws and regulations, as well as the laws of other countries, that establish health and environmental quality standards. These standards, among others, relate to air and water pollutants and the management and disposal of hazardous substances and wastes. We are exposed to potential liability for personal injury or property damage caused by any release, spill, exposure or other accident involving such pollutants, substances or wastes.
In connection with the historical operation of our facilities, including those associated with acquired operations, substances which currently are or might be considered hazardous were used or disposed of at some sites that will or may require us to make expenditures for remediation. In addition, we have agreed to indemnify parties from whom we have purchased or to whom we have sold facilities for certain environmental liabilities arising from acts occurring before the dates those facilities were transferred.
We believe we are in compliance, in all material respects, with environmental laws and regulations and maintain insurance coverage to mitigate our exposure to environmental liabilities. We do not believe any environmental matters will have a material adverse effect on our future results of operations, financial position or cash flow. We do not anticipate we will incur material capital expenditures for environmental controls or for the investigation or remediation of environmental conditions during the remainder of 2015 or 2016.
Item 1A. Risk Factors
There have been no material changes to risk factors as previously disclosed in our 2014 Annual Report on Form 10-K for the year ended December 31, 2014 filed with the SEC on February 25, 2015.
Item 2. Unregistered Sales of Equity Securities and Use of Proceeds
None.
Item 3. Defaults Upon Senior Securities
None.
Item 4. Mine Safety Disclosures
None.
Item 5. Other Information
Effective July 22, 2015, we entered into a note purchase and guarantee agreement to issue $200.0 million of senior notes (the "New Senior Note") in a private placement among Chicago Bridge & Iron Company (Delaware), as issuer (the "Issuer"), CB&I as Parent Guarantor, Merrill Lynch, Pierce, Fenner & Smith Incorporated and Credit Agricole as joint placement agents, and each of the purchasers party thereto. Interest is due semi-annually at a fixed rate of 4.53%, with principal of $200.0 million due in July 2025.
The New Senior Note permits the proceeds thereunder to be used for working capital, capital expenditures, share repurchases, other ordinary course requirements, in addition to mergers and acquisitions, subject to certain conditions, and has financial and restrictive covenants and events of default similar to those of our Senior Notes.
The New Senior Note is the Issuer's senior unsecured obligation which ranks equally in right of payment with all of its other unsubordinated indebtedness. The New Senior Note is guaranteed on a senior unsecured basis by CB&I and each of its subsidiaries executing the Subsidiary Guarantee Agreement.
The Issuer has the option to prepay the New Senior Note at any time and from time to time, and in whole, or in part, at 100% of the principal amount prepaid, plus accrued and unpaid interest to the prepayment date, plus a "make-whole" premium as specified in the agreement. The Issuer must offer to prepay the New Senior Note upon the occurrence of any change of control or the execution of an agreement which, if performed, would result in a change of control, at the price of 100% of the principal amount thereof, plus accrued and unpaid interest thereon to the prepayment date.
The foregoing description of the New Senior Note does not purport to be complete and is qualified in its entirety by reference to the complete text of the New Senior Note agreement as filed as Exhibit 10.5 to this Form 10-Q.

43

Table of Contents

Item 6. Exhibits
(a) Exhibits
 
10.1 (2)
 
Amended and Restated Revolving Credit Agreement, dated as of July 8, 2015, by and among Chicago Bridge & Iron Company N.V., Chicago Bridge & Iron Company (Delaware), as the Initial Borrower, certain Subsidiaries of Chicago Bridge & Iron Company N.V. party thereto, as Designated Borrowers, Bank of America, N.A., as Administrative Agent, Swing Line Lender and L/C Issuer, and the lenders party thereto, and the agents party thereto.
 
 
 
10.2 (2)
 
Amendment No. 3 dated July 8, 2015, to the Revolving Credit Agreement, dated as of October 28, 2013, by and among Chicago Bridge & Iron Company N.V., Chicago Bridge & Iron Company (Delaware), as the Initial Borrower, certain Subsidiaries of Chicago Bridge & Iron Company N.V. party thereto, as Designated Borrowers, Bank of America, N.A., as Administrative Agent, the lenders party thereto and the agents party thereto.
 
 
 
10.3 (2)
 
Term Loan Agreement, dated as of July 8, 2015, by and among Chicago Bridge & Iron Company N.V., Chicago Bridge & Iron Company (Delaware), as Borrower, Bank of America, N.A., as Administrative Agent, the lenders party thereto, and the agents party thereto.
 
 
 
10.4 (2)
 
Amendment No. 3 dated July 8, 2015, to the Term Loan, dated as of December 21, 2012, by and among Chicago Bridge & Iron Company N.V., Chicago Bridge & Iron Company (Delaware), as Borrower, Bank of America, N.A., as Administrative Agent, the lenders party thereto and the agents party thereto.
 
 
 
10.5 (1)
 
Note Purchase and Guarantee Agreement dated as of July 22, 2015, by and among Chicago Bridge & Iron Company N.V., Chicago Bridge & Iron Company (Delaware) and each of the purchasers party thereto.
 
 
 
31.1 (1)
 
Certification Pursuant to Rule 13-14(a) of the Securities Exchange Act of 1934, as adopted pursuant to Section 302 of the Sarbanes-Oxley Act of 2002.
 
 
31.2 (1)
 
Certification Pursuant to Rule 13-14(a) of the Securities Exchange Act of 1934, as adopted pursuant to Section 302 of the Sarbanes-Oxley Act of 2002.
 
 
32.1 (1)
 
Certification Pursuant to 18 U.S.C. Section 1350, as adopted pursuant to Section 906 of the Sarbanes-Oxley Act of 2002.
 
 
32.2 (1)
 
Certification Pursuant to 18 U.S.C. Section 1350, as adopted pursuant to Section 906 of the Sarbanes-Oxley Act of 2002.
 
 
101.INS (1),(3)
 
XBRL Instance Document.
 
 
101.SCH (1),(3)
 
XBRL Taxonomy Extension Schema Document.
 
 
101.CAL (1),(3)
 
XBRL Taxonomy Extension Calculation Linkbase Document.
 
 
101.DEF (1),(3)
 
XBRL Taxonomy Extension Definition Linkbase Document.
 
 
101.LAB (1),(3)
 
XBRL Taxonomy Extension Label Linkbase Document.
 
 
101.PRE (1),(3)
 
XBRL Taxonomy Extension Presentation Linkbase Document.
 
(1)
Filed herewith
(2)
Incorporated by reference from the Company's 2015 Form 8-K filed July 14, 2015
(3)
Attached as Exhibit 101 to this report are the following documents formatted in XBRL (Extensible Business Reporting Language): (i) the Condensed Consolidated Statements of Operations for the three and six months ended June 30, 2015 and 2014, (ii) the Condensed Consolidated Statements of Comprehensive Income for the three and six months ended June 30, 2015 and 2014, (iii) the Condensed Consolidated Balance Sheets at June 30, 2015 and December 31, 2014, (iv) the Condensed Consolidated Statements of Cash Flows for the six months ended June 30, 2015 and 2014, (v) the Condensed Consolidated Statements of Changes in Shareholders’ Equity for the six months ended June 30, 2015 and 2014, and (vi) the Notes to Financial Statements.


44

Table of Contents

SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.
 

 
 
 
Chicago Bridge & Iron Company N.V.
 
 
 
By:
Chicago Bridge & Iron Company B.V.
 
 
 
Its:
Managing Director
 
 
 
 
 
 
 
 
 
Date:
July 24, 2015
 
By: 
/s/ Michael S. Taff
 
 
 
 
Michael S. Taff
 
 
 
 
Managing Director
 
 
 
 
(Principal Financial Officer and Duly Authorized Officer)


45